You are a project manager working on contract. You’ve performed earned value analysis and discovered that the project will be completed on time and under the original estimated amount. This means the profit to your company will decrease as will your personal bonus. Which of the following should you do?
A. Add activities to the project to increase the cost enough to meet the original estimated amount.
B. Tell the customer you're adding additional requirements to the project chat were originally cut because of cost constraints.
C. Inform the customer that the project is completed and has come in under budget.
D. Bill the customer for the full amount of the contract as this was the original agreed-upon price.
No Answer is Posted For this Question
Be the First to Post Answer
Which of the following project-scheduling techniques allows for conditional and probabilistic treatment? A. GERT B. CPM C. PERT D. CPM and PERT
Critical path tasks are those tasks that: A. Have equal pessimistic, optimistic, and most likely estimated times B. Have a float rime of zero C. Have the same start date D. Have multiple early start dates and early finish dates
What are the 10 knowledge areas of project management?
Your procurement department has obtained independent estimates. The vendor's proposal is substantially different than the independent estimates. All of the following are true except: A. The SOW was not detailed enough. B. The vendor failed to respond according to the terms of the proposal. C. The vendor failed to respond to all items in the SOW. D. The vendor failed to respond to all items in the contract.
Halloween is approaching fast. Your market research shows that the little yellow chicks and pink bunny marshmallow candies are the best-selling candy at Easter time, outselling all other types of candies. This prompts the company to introduce a new version of marshmallow candies with Halloween themes this season. Which of the following is true? A. This project came about due to customer request, and the primary constraint is time B. This project came about due to market demand, and the primary constraint is time. C. This project came about due to market demand, and the primary constraint is quality. D. This project came about due to customer request, and the primary constraint is quality.
As a PMP, you will be required to comply with the Project Management Professional Code of Professional Conduct. Part of your responsibility concerns applying professional knowledge. All of the following are part of applying professional knowledge except: A. Developing relationships based on mutual respect B. Staying abreast of project management practices C. Keeping up with industry trends and new technology D. Honestly reporting your project management experience
Common causes of variances are a result of all of the following except: A. Random variances B. Predictable variances C. Special variances D. Variances that are always present in the process
You know that PV = 475, AC = 430, EV = 480, EAC = 40, and BAC = 525. What is VAC? A. 440 B. 390 C. 485 D. 435
Which of the following tools and techniques shows the impacts of one decision over another as well as the probability and cost of each risk along a logical path? A. Simulation B. Decision tree C. Probability/impact risk matrix D. Sensitivity analysis
When a project is being performed under contract, the product description is provided by which of the following? A. The buyer B. The project sponsor C. The project manager D. The contractor
All of the following are inputs to the Administrative Closure process except: A. Performance measurement documentation B. Product documentation C. Other project records D. Contract documents
You are a project manager for a growing dairy farm. They offer their organic dairy products regionally and are expanding their operations to the West Coast. They're in the process of purchasing and leasing dairy farms to get operations under way. The sub project manager in charge of network operations has reported some hardware problems to you. You’re also having some other coordinating and integrating other elements of the project. Which of the following is true? A. You are in the Project Plan Execution process. B. Your project team doesn't appear to have the right skills and knowledge needed to perform this project. C. You are in the Information Distribution process. D. Your project team could benefit from some team-building exercises.