You are the project manager for a top-secret software project for an agency of the United States Government. Your mission, should you choose to accept it, is to complete the project using internal resources. The reason is because getting top secret clearances for contractors takes quite a bit of time and waiting for clearances would jeopardize the implementation date. Your programmers are 80 percent of the way through the programming and testing work when your agency appoints a new executive director. Your programmer’s are siphoned off this project to work on the executive director's hot new project. Which of the following addresses the purpose of Scope Verification in this case?
A. It determines the correctness and completion of all the work
B. It documents the level and degree of completion
C. It determines if the project results comply with quality standards
D. It documents the correctness of the work according to stakeholders' expectations
No Answer is Posted For this Question
Be the First to Post Answer
You are an international project manager from the United States living in a foreign country. The project you're working on has lasted two-and-a-half years. During that time, you've really gotten to feel comfortable in the foreign country and have enjoyed living in their culture. The project has just ended, and you've returned to the United States. Upon your return, you're surprised to find that you're feeling a little disoriented as you've gotten so used to the foreign culture and its slower pace that you've forgotten what some things are like in the US. This experience is known as: A. Diversity shock B. Global norming C. Culture shock D. Culture norming
what kind of questions can be asked from SDLC for a project leader role?
How project comes to a software company? what is the role of sales department,marketing department,delivery manager,project manager in a software development? simply,what is project life cycle?
What is one of the problems with project management software? A. The project manager manages the software instead of the project B. Project duration calculations are sometimes approximate. C. You cannot override the project management software decisions regarding schedules. D. It’s expensive and difficult to use.
You are the project manager for a nonprofit organization. Your project has come about due to a social need. Your sponsor wants to get right to the Planning process. However, you know that a scope statement should be published prior to proceeding to the Planning processes. All of the following are true regarding scope statements except: A. It documents roles and responsibilities. B. It can be modified to reflect changes to the scope of the project. C. It describes the project deliverables, requirements, and objectives D. It serves as a baseline for future project decisions.
You need to convey some very complex, detailed information to the project stakeholders. The best method of communicating this kind of information is? A. Verbal B. Vertical C. Horizontal D. Written
What is the w5hh (wwwwwhh) principle given by barry boehm?
You have collected the performance measurement documentation for your project to be included in the project archives. What is the purpose of the performance measurement documentation? A. It's used as part of the formal acceptance process to verify contract expenditures. B. It's reviewed to make certain the project goals and objectives were met. C. It's included in the project archive documentation after confirming the accuracy of the measurements. D. It’s used as historical information for future project that are similar in scope to this project.
How do you ensure that your project is always on track?
product development vs IT services
Which of the following processes are performed in the Closing process group and in what order? A. Administrative Closure then Contract Closeout B. Scope Verification then Administrative Closure C. Contract Closeout then Scope Verification D. Contract Closeout then Administrative Closure
Your project was just completed, accepted, and closed. As is customary for your organization, you conduct a post-implementation audit. The purpose of this audit includes all of the following except: A. Evaluating project goals and comparing them to project product B. Reviewing successes and failures C. Documenting the acceptance of the work results D. Documenting possible improvements for future projects