Which of the following processes assess the likelihood of risk occurrences and their consequences using numeric probability assignments?
A. Qualitative Risk Analysis
B. Risk Identification
C. Quantitative Risk Analysis
D. Risk Response Planning
No Answer is Posted For this Question
Be the First to Post Answer
During contract negotiations, your vendor tells you that the equipment originally bid in the RFP is no longer available. They say the best solution is to buy the new equipment they're offering, which is a higher price than the original equipment. You have concerns that the new equipment might not be compatible with existing equipment and try to discuss this with them. They remind you that this decision was already made during the last contract negotiation meeting so there's no need to continue to discuss it. This is an example of which of the following? A. Proposal B. Compromise C. Storming D. Fair accomplish
The Critical Path Method is a mathematical tool and technique of the Schedule Development process. All of the following are true regarding CPM except: A. Determines a single early and late start date and a single early and late finish date B. Calculates expected value C. Focuses on the calculation of float time D. Shows the critical path, or the path with the longest duration
What type of organization experiences the least amount of stress during project closeout? A. Projectized B. Functional C. Weak matrix D. Strong matrix
The product description, strategic plan, project selection criteria, and historical information are considered: A. Inputs to the project Planning process B. Inputs to the project Overview process C. Inputs to the project Initiation process D. Inputs to the project Execution process
Your project sponsor has requested a cost estimate for the project. She would like the cost estimate to be as accurate as possible as this might be her one and only chance to secure the budget for this project due to recent cuts in special projects. You decide: A. To use analogous estimating techniques B. To use bottom-up estimating techniques C. To use top-down estimating techniques D. To use expert judgment techniques
You are the project manager for your company's annual Spring Fling. You've made all the plans and reserved the outdoor grounds for the appropriate day and time. You are now two days away from the big day, and the forecast is calling for light rain showers in the afternoon. You rented tents just in case this risk occurred. This is an example of which Risk Response Planning tool and technique? A. Passive acceptance B. Contingency planning C. Avoidance D. Transference
You are a project manager for Picture Shades, Inc. They manufacture window shades for hotel chains that have replicas of Renaissance-era paintings on the inside of the shades. Picture Shades is taking their product to the home market, and you're managing the new project. They will offer their products at retail stores as well as on their website. You're developing the project schedule for this undertaking and have determined the critical path. Which of the following is true? A. You calculated the most likely start date and most likely finish dates, float time, and weighted average estimates. B. You calculated the activity dependency, and the optimistic and pessimistic activity duration estimates. C. You calculated the early and late start dates, early and late finish dates, and float times for all activities. D. You calculated the optimistic, pessimistic, and most likely duration times and the float times for all activities.
Receivers in the communication model filter their information through all of the following except: A. Culture B. Knowledge of subject C. Conflict D. Language
Project managers spend what percentage of their prime communicating? A. 90 B. 85 C. 75 D. 50
The lowest level of the WBS is called what? A. Code of accounts B. Requirement C. Milestone D. Work package
Intellectual property includes all of the following except: A. Software B. Patents C. Hardware D. Business processes
You are a project manager for Bluebird Technologies. Bluebird writes custom billing applications for several industries. One of your users verbally requests changes to one of the screen displays. You explain to her that the change needs to go through the change control system. You explain that a change control system does all of the following, except: A. Document procedures for change requests B. Track the status of change requests C. Describe the management impacts of change D. Determine if changes are approved or denied