You've constructed the WBS for your recent project. Level two assignments have been made, and you've requested that the sub project manager’s report back to you in 3 weeks with each of their individual WBS constructed. All of the following are true except:
A. The work package level facilitates resource assignments.
B. The work package level is the lowest level in the WBS.
C. The work package level defines the agreed-upon deliverables.
D. The work package level facilitates cost and time estimates. ?
No Answer is Posted For this Question
Be the First to Post Answer
How do you handle change request?
Which of the following is true regarding the project charter? A. The project charter should be published under the name of a manager external to the project. B. The project charter should be published under the project sponsor's name. C. The project charter should be published under the name of the project manager. D. The project charter should be published under the name of the project champion.
Your project sponsor has requested a cost estimate for the project you're working on. This project is similar in scope to a project you worked on last year. She would like to get the cost estimates as soon as possible. Accuracy is not her primary concern right now. She needs a ball park figure by tomorrow. You decide to use: A. Analogous estimating techniques B. Bottom-up estimating techniques C. Parametric modeling techniques D. Computerized modeling techniques
You are a contract project manager for a wholesale flower distribution company. Your project is to develop a website for the company that allows retailers to place their flower orders online. You will also provide a separate link for individual purchases that are ordered. This project involves coordinating the parent company, growers, and distributors. You are preparing a performance review and have the following measurements at hand: PV = 300; AC = 200; and EV = 250. What is the CPI of this project? A. 0.80 B. 1.25 C. 1.5 D. 0.83
You know that the next status meeting will require some discussion and a decision for a problem that has surfaced on the project. In order to make the most accurate decision, you know that the number of participants in the meeting should be limited to: A. 1 to 5 B. 5 to 11 C. 7 to 16 D. 10 to 18
During a recent team meeting, you reached a resolution to a problem that's been troubling the team for several weeks. You took responsibility for searching out the facts of this problem and uncovered the right answer to this problem. You presented the facts at the project status meeting, and everyone reached agreement on the recommended solution based on the facts you presented. This is an example of what type of conflict resolution technique? A. Compromise B. Smoothing C. Confrontation D. Forcing
You are preparing a diagram that plots two variables, the dependent variable and the independent variable, to see the relationship between the two elements. What kind of diagram are you using? A. Cause-and-effect diagram B. Control chart C. Flowchart D. Scatter diagram
What are the triple constraints? A. Time, schedules, and quality B. Time, availability, and quality C. Time, money, and schedules D. Time, money, and quality
You are a project manager responsible for the construction of a new office complex. You are taking over for a project manager who recently left the company. The prior project manager completed the scope statement and scope management plan for this project. In your interviews with some key stakeholders, you conclude which of the following? A. They understand that the scope statement assesses the Stability of the project scope and outlines how to incorporate scope changes into the project. B. They understand that the scope management plan assesses the stability of the project scope and outlines how to incorporate scope changes into the project. C. They understand that the scope management plan is deliverables oriented and cost estimates can be easily derived it. D. They understand that the scope statement is deliverables oriented and cost estimates can be easily derived from it.
You are a project manager with technical expertise in the pharmaceutical industry. You've decided to try your hand at project management in the entertainment industry. Which of the following is true? A. You will likely be successful because communication skills are your strong suit. You anticipate having technical experts on your project team to address industry specifics that you're not familiar with. B. You will likely be successful because your organizational skills are excellent. You anticipate having technical experts on your project team to address industry specifics that you're not familiar with. C. You will probably be successful because you have a friend in the entertainment industry that has briefed you on all the important aspects of this project that you'll need to know. You anticipate having technical experts on your project team to address industry specifics that you're not familiar with. D. You will probably not be successful because you have little knowledge of the entertainment industry even though you anticipate having technical experts on your project team to address industry specifics that you're not familiar with.
Your selection committee meets on a semiannual basis. They've determined that projects must meet or exceed a specific profit limit in order to be accepted and prioritized on the project list. Which of the following is true? A. The selection committee has defined project selection criteria, which is a tool and technique of Initiation. B. The selection committee has defined project selection methods, which is a tool and technique of Initiation. C. The selection committee has defined project selection methods, which is an input to Initiation. D. The selection committee has defined project selection criteria, which is an input to Initiation.
You know that PV = 475, AC = 430, EV = 480, EAC = 40, and BAC = 525. What is VAC? A. 440 B. 390 C. 485 D. 435