Your selection committee meets on a semiannual basis. They've determined that projects must meet or exceed a specific profit limit in order to be accepted and prioritized on the project list. Which of the following is true?
A. The selection committee has defined project selection criteria, which is a tool and technique of Initiation.
B. The selection committee has defined project selection methods, which is a tool and technique of Initiation.
C. The selection committee has defined project selection methods, which is an input to Initiation.
D. The selection committee has defined project selection criteria, which is an input to Initiation.
No Answer is Posted For this Question
Be the First to Post Answer
You are a project manager for Dutch Harbor Consulting. Your latest project involved the upgrade of an organization's operating system on 236 servers. You performed this project under contract. You are in the Contract Closeout process and have reviewed the contracting process to identify lessons learned. What is the name of the tool and technique of Contract Closeout you used to perform this function? A. Procurement audits B. Performance reviews C. Performance audits D. Procurement reviews
Which of the following describes a unique characteristic of the project Executing and Controlling processes? A. The core processes in the Executing and Controlling processes are from the Project Integration knowledge area from the Project Integration knowledge area. B. Both the Executing and Controlling processes measure variances in project performance and use corrective action to bring performance hack in line with the plan. C. Executing is an input to the Controlling processes, and Controlling is an input to Execution. D. Executing and controlling each have only one core process.
Which of the following is true? A. Discounted cash flow analysis is the least precise of the cash flow techniques as it does not consider the time value of money. B. NPV is the least precise of the cash flow analysis techniques as it assumes reinvestment at the discount rate. C. Payback period is the least precise of the cash flow analysis techniques as it does not consider the time value of money. D. IRR is the least precise of the cash flow analysis techniques because it assumes reinvestment at the cost of capital.
What are the five project management process groups, in order? A. Initiation, Executing, Planning, Controlling, and Closing B. Initiation, Controlling, Planning, Executing, and Closing C. Initiation, Planning, Controlling, Executing, and Closing D. Initiation, Planning, Executing, Controlling, and Closing
What are the skills required to be a project manager? Followup question, Rate yourself in each of the skill with examples.
18 Answers Cognizant, Microsoft,
You are going to lake some performance measurements for your current project. You know that PV = 450, AC = 500, and EV= 375. What is the CPI and SPI respectively? A. CPI = .90, and SPI = 1.2. B. CPI = .75, and SPI = .83. C. CPI = 1.2, and SPI = .90. D. CPI = .83, and SPI = .75.
You are the project manager for a large construction project. The project objective is to construct a set of outbuildings to house the Olympic support team that will be arriving in your city 18 months from the project start date. Resources are not readily available as they are currently assigned to other projects. Jack, an expert crane operator, is needed for this project two months from today. Which of the following skills will you use to get Jack assigned to your project? A. Negotiation and influencing skills B. Communication and organizational skills C. Communication skills D. Problem-solving skills
The Project which is handled by you is in RED, customer has given you 4 weeks to show improvement, still nothing has worked out. The Customer again gives 3 weeks to improve and you do your best to improve, but nothing works out. Now the customer is not at all happy, HOW TO CONVINCE THIS CUSTOMER ???
8 Answers AZS, BGR Energy, Wipro,
What is the meaning of scope of the project?
As a project manager, you're responsible for maintaining and ensuring integrity for all of the following except: A. Personal integrity of others B. Project management process C. Personal integrity D. Product integrity
You are a project manager with several years of experience in project management. You’ve just accepted your first project in a foreign country. You've been in the country a week or two and are experiencing some disoriented feelings. This is known as: A. Collocation B. Diversity shock C. Global culturing D. Culture shock
You are the project manager for a new website for the local zoo. You need to perform Qualitative Risk Analysis. When you've completed this process, you'll produce all of the following outputs except: A. Overall risk ranking for the project B. List of prioritized risks C. Inputs to other processes D. List of risks for additional analysis and management