Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


Halloween is approaching fast. Your market research shows that the little yellow chicks and pink bunny marshmallow candies are the best-selling candy at Easter time, outselling all other types of candies. This prompts the company to introduce a new version of marshmallow candies with Halloween themes this season. Which of the following is true?
A. This project came about due to customer request, and the primary constraint is time
B. This project came about due to market demand, and the primary constraint is time.
C. This project came about due to market demand, and the primary constraint is quality.
D. This project came about due to customer request, and the primary constraint is quality.


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

Common causes of variances are a result of all of the following except: A. Random variances B. Predictable variances C. Special variances D. Variances that are always present in the process

0 Answers  


Which of the following are tools and techniques of the Initiation process? A. Project selection methods and expert judgment B. Project selection criteria and expert judgment C. Constraints and assumptions and expert judgment D. Expert judgment and project charter

0 Answers  


Which of the following is true regarding the scope statement? A. It describes how to make changes to project scope. B. It describes project deliverables and serves as a baseline for future project decisions. C. It assesses the stability of the project scope and is a baseline for future project decisions. D. It assesses the reliability of the project scope and describes the frequency of changes and their impacts.

0 Answers  


What is the key activity during Contract Closeout and Administrative Closure? A. Documenting lessons learned B. Creating project archives C. Disseminating information to formalize project closure D. Documenting project closure

0 Answers  


The lowest level of the WBS is called what? A. Code of accounts B. Requirement C. Milestone D. Work package

0 Answers  


How to track your team members?

0 Answers  


All of the following strategies are tools and techniques of Risk Response Planning used to reduce or control risk except? A. Mitigation B. Simulation C. Avoidance D. Acceptance

0 Answers  


Deliverables can be described as: A. The purpose for undertaking the project B. The verifiable results of products or services that must be produced to consider the project complete C. The specifications regarding the goals of the project that must be produced to consider the project complete D. The measurable outcomes of the project goals

0 Answers  


Your procurement department has obtained independent estimates. The vendor's proposal is substantially different than the independent estimates. All of the following are true except: A. The SOW was not detailed enough. B. The vendor failed to respond according to the terms of the proposal. C. The vendor failed to respond to all items in the SOW. D. The vendor failed to respond to all items in the contract.

0 Answers  


What is the name of the unplanned response used to deal with negative risk events in the Risk Monitoring and Control process? A. Mitigation B. Contingency plans C. Workarounds D. Corrective action

0 Answers  


Which performance measurement tells us how much more of the budget is required to finish the project? A. ETC B. EV C. AC D. EAC

0 Answers  


Three people are responsible for establishing cost of quality theories. Crosby and Juran are two of them, and their theories respectively are: A. Grades of quality, fitness for use B. Fitness for use, zero defects C. Zero defects, fitness for use D. Cost of quality, zero defects

0 Answers  


Categories