Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

The VP of marketing approaches you and requests that you change the visitor logon screen on the company’s website to include a username with at least six characters. This is considered:
A. Project initiation
B. Ongoing operations
C. A project
D. Project execution

Answer Posted / hafiz muhammad zeeshan

B. Ongoing operations

Explanation: Projects exist to create a unique product or service. The logon screen in this question is not a unique product. A minor change has been requested, indicating this is an ongoing operation function. Some of the criteria for projects are that they are unique, temporary with definitive start and end dates, and considered complete when the project goals are achieved.

Is This Answer Correct ?    0 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Describe function-oriented metrics.

934


The Project Integration Management knowledge area is made up of which of the following processes? A. Initiation, Project Plan Development, and Integrated Change Control B. Project Plan Development, Project Plan Execution, and Integrated. C. Project Plan Development, Initiation, and Scope Planning D. Initiation, Scope Planning, and Integrated Change Control

1035


You are a project manager for Candy Works candy factory. Your project involves reporting information from the newly installed candy-counting machine to the financial system. This will give executives the ability to see production run counts at any time during the day. You need to purchase an expensive piece of hardware as part of this project. One of the vendors bidding on the project is a close friend. In order to win the bid, she needs to know how much money the company is willing to spend on the equipment and consulting. Your friend asks you to give her this confidential information and not tell anyone you did. Which of the following is the most appropriate response? A. Tell your friend that as a PMP, you're required to abide by the Project Management Professional Code of Professional Conduct and this would violate the code as it's a conflict of interest. B. Tell your friend that as a PMP, you're required to abide by the Project Management Professional Code of Professional Conduct and this would violate the code as it’s a personal gain. C. Tell your friend that as a PMP, you're required to abide by the Project Management Professional Standards and Ethics Code and this would violate the code as it’s a conflict of interest. D. Tell your friend that as a PMP, you’re required to abide by the Project Management Professional Standards and Ethics Code and this would violate the code as it’s an ethics violation.

1100


You are a project manager for Laurel’s theater productions. Your new project is coming in over budget and requires a cost change through the cost change control system. The cost variance was projected using which of the following tools and techniques? A. Performance measurements B. Cost baseline measurements C. Computerized tools D. Performance reports

1064


You are a project manager for Star Light Strings. Star Light manufactures strings of lights for outdoor display. Their products range from simple light strings to elaborate lights with animal designs, bug designs, memorabilia, and so on. Your newest project requires a scope change. You have documented the characteristics of the product and its functionality using which of the following tools and techniques? A. Change control system B. Corrective action C. Configuration management D. Updates to the scope management plan

1078


Your company. Kick That Ball Sports, has appointed you project manager for their new Cricket product line introduction. This is a national effort, and all the retail stores across the country need to have the new products on the shelves before the media advertising blitz begins. The product line involves three new products, some with multiple deliverables. The Scope Definition process is now complete. Which of the following is true? A. The WBS template, an output of the Scope Definition process, was used from the previous project to create the WBS for this project. The WBS encompasses the major deliverables for the project. B. The WBS template from the previous project, an output from the Scope Planning process, was used to create the WBS for this project. The WBS encompasses the major deliverables for the project. C. The WBS, an output of the Scope Planning process, has been created, and it encompasses the full scope of work for the project. D. The WBS, an output of the Scope Definition process, has been created, and it encompasses the full scope of work for the project.

1537


Project managers have the highest level of authority and the most power in which type of organizational structure? A. Projectized B. Strong matrix C. Functional D. Balanced matrix

1098


You are a project manager for a growing dairy farm. They offer their organic dairy products regionally and are expanding their operations to the West Coast. They're in the process of purchasing and leasing dairy farms to get operations under way. The sub project manager in charge of network operations has reported some hardware problems to you. You’re also having some other coordinating and integrating other elements of the project. Which of the following is true? A. You are in the Project Plan Execution process. B. Your project team doesn't appear to have the right skills and knowledge needed to perform this project. C. You are in the Information Distribution process. D. Your project team could benefit from some team-building exercises.

890


What are the Initiation process outputs? A. Project charter, historical information, and project manager identification and assignment B. Project charter, project manager identification and assignment, constraints, and assumptions C. Project charter, historical information, constraints, and assumptions D. Project charter, constraints, and assumptions

1041


You are a project manager for Waterways Houseboats, Inc. You have been asked to perform a benefit/cost analysis for two proposed projects. Project A costs $2.4 million with potential benefits of $12 million and future operating cost of $3 million. Project B costs $2.8 million with potential benefits of $14 million and future operating costs of $2 million. Which project should you recommend? A. Project A because the cost to implement is cheaper than Project B B. Project A because the potential benefits plus the future operating costs are less in value than the same calculation for Project B C. Project B because the potential benefits minus the implementation and future operating costs are greater in value than the same calculation for Project A D. Project B because the potential benefits minus the costs to implement are greater in value than the same calculation for Project A

1119


What is one of the advantages of a functional structure? A. All employees report to one manager and have a clear chain of command. B. All employees report to two or more managers, but project team members show loyalty to functional managers. C. The organization is focused on projects and project work. D. Teams are collocated.

972


You are the project manager for the Late Night Smooth Jazz Club chain, with stores in 12 states. Smooth Jazz is considering opening a new club in Kansas City or Spokane. You have derived the following information: Project Kansas City: The payback period is 27 months, and the IRR is 35 percent. Project Spokane: The payback period is 25 months, and the IRR is 32 percent. Which project should you recommend to the selection committee? A. Project Spokane because the payback period is shortest B. Project Kansas City because the IRR is highest C. Project Spokane because the IRR is lowest D. Project Kansas City because the payback period is longest ?

1056


You are the project manager for a new construction project in your city. Your longtime personal friend is bidding on the project. They've asked you to give them an indication of the budget for this project so that they do not overbid and lose the deal. What is the most appropriate response? A. Give the information to your friend. You know their character and can trust that they won't tell anyone. B. Tell your friend that after all this time, they should know you better than to think you'd put your personal integrity on the line or compromise your job due to a conflict of interest. Decline to give them the information. C. Tell your friend you'll give them the information if they'll promise not to tell anyone and if they'll agree to help you out with some materials on your basement-refinishing project. D. Give the information to your friend and inform the project sponsor so that the information can be shared with the other bidders as well.

890


You are a project manager working in a foreign country. You observe that some of your project team members are having a difficult time adjusting to the new culture. You provided them training on cultural differences and the customs of this country before arriving, but they still seem uncomfortable and disoriented. Which of the following is true? A. This is the result of working with teams of people from two different countries. B. This condition is known as culture shock. C. This is the result of jet lag and travel fatigue. D. This condition is known as global culturalism.

1120


You know that BAC = 375, PV = 300, AC = 200, and EV = 250. Variances that have occurred on the project to date are not expected to continue. What is the ETC? A. 75 B. 50 C. 125 D. 150

1456