A can do a piece of work in 20 days.B can do the same in 15 days.they both together work for 6 days,then B is replaced by C who works with A for next 4 days & finished it.in how many days C alone can do the same work?
Answers were Sorted based on User's Feedback
Answer / dipesh
Work done by A in one day is 1/20
Work done by B in one day is 1/15
Work done by A and B in 6 days is (1/20+1/15)*6
Work done by A and C in 4 days is (1/20+1/x)*4 // assuming that C does the complete work in x days)
Now we need to find out the value of x from following
(1/20+1/15)*6 + (1/20+1/x)*4 = 1
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / archana
Answer: C can complete the work in 5 days
work done by A in one day= 1/20
work done by B in one day= 1/15
work done by A and B together in one day= 1/6
work done by A and C together in one day= 1/4
work done by C alone in one day= work done by A and C in one day - work done by A in one day
=(1/4)-(1/20)= 1/5
work done by C alone= 5 days
Is This Answer Correct ? | 0 Yes | 2 No |
simla pact was signed by
If two pencils cost 8 cents, then how much do 5 pencils cost?
who was the first one day captain of Indian cricket team?
how many numbers upto 2oo which are divisible by 2 11 ?
X < 0, Y <> 0 then what is the possibility that the result is always positive?
on an item a company gave 25% discount then they get 25% profit if it gives 10% discount then what is the profit.
guttural : throat :: gastric :
A driver drives at a speed of 72kmph in a highway. Another driver drives at the speed of 25 m/sec . find the difference in their speeds in m/sec. ?
what we do exactly before drinking water?
If 1/x = 3.5. then 1/(x+2) =
8 to the power of x is 32,what is the value of x?
Find out the Simple Interest paid for a sum of $4000 at the rate of 8% per annum for 3 months.