what would be the test plan for agile testing??
Answer / uday
When it comes to Agile process, we should not call it as
Test Plan.
In Agile methodology, we call "product backlog" and "sprint
backlog". Because agile is time boxed and is divided into
Iterations, we will take few tasks from Product backlog to
Sprint backlog on priority basis.
In Sprint backlog we will tell like what items are assigned
to each individual and their timelines. And the progress is
measured in Burn down charts.
So companies which follow strict Agile will not have Agile
Test Plan, rather they call it as Sprint backlog.
Correct me if anything mentioned above is not accurate.
| Is This Answer Correct ? | 4 Yes | 1 No |
What certifications can a tester of less than 1 yr experience go for? which is the best certification and how many months of preparation is required?
What r SQA activities?
12 Answers Amazon, Call Centre, MBT,
The person who is week in writing code.what the best option --join Testing course and .net Course..Which one is better..
What do you mean by trend analysis?
Why is incremental integration preferred over 'big bang' integration?
A testing process that exercises a software system's coexistence with others by taking multiple integrated systems that have passed system testing as input and tests their required interactions.
Explain basis path testing?
Send me the interview questions
What is Mainframe testing all about? What is testing methodology which applies to this kind of testing? Can anyone with the basic knowledge of mainframe system can apply for the Mainframe testing job requirement?
What is parameter?
Find odd man out related to EA a) Play fish b) Take2 c) Hasbro d) Pogo
How to answer when the interviewer asked "what is your project architecture?" pls. tell me in general ..