Which of the following would be considered an essential
feature of a network management system?
A. A graphical interface to map the network topology
B. Capacity to interact with the Internet to solve the problems
C. Connectivity to a help desk for advice on difficult issues
D. An export facility for piping data to spreadsheets
Answer / guest
Answer: A
To trace the topology of the network it would be essential
that a graphical interface exist. It is not necessary that
each network be on the Internet and a help desk, and the
ability to export to a spreadsheet is not an essential element.
| Is This Answer Correct ? | 3 Yes | 0 No |
When an information security policy has been designed, it is MOST important that the information security policy be: A. stored offsite. B. written by IS management. C. circulated to users. D. updated frequently.
The PRIMARY objective of an IS audit function is to: A. determine whether everyone uses IS resources according to their job description. B. determine whether information systems safeguard assets, and maintain data integrity. C. examine books of accounts and relative documentary evidence for the computerized system. D. determine the ability of the organization to detect fraud.
Which of the following translates e-mail formats from one network to another so that the message can travel through all the networks? A. Gateway B. Protocol converter C. Front-end communication processor D. Concentrator/multiplexor
As a business process reengineering (BPR) project takes hold it is expected that: A. business priorities will remain stable. B. information technologies will not change. C. the process will improve product, service and profitability. D. input from clients and customers will no longer be necessary.
While reviewing an ongoing project, the IS auditor notes that the development team has spent eight hours of activity on the first day against a budget of 24 hours (over three days). The projected time to complete the remainder of the activity is 20 hours. The IS auditor should report that the project: A. is behind schedule. B. is ahead of schedule. C. is on schedule. D. cannot be evaluated until the activity is completed.
The MAJOR advantage of the risk assessment approach over the baseline approach to information security management is that it ensures: A. information assets are over protected. B. a basic level of protection is applied regardless of asset value. C. appropriate levels of protection are applied to information assets. D. an equal proportion of resources are devoted to protecting all information assets.
Applying a retention date on a file will ensure that: A. data cannot be read until the date is set. B. data will not be deleted before that date. C. backup copies are not retained after that date. D. datasets having the same name are differentiated.
When planning an audit of a network set up, the IS auditor should give highest priority to obtaining which of the following network documentation? A. Wiring and schematic diagram B. Users list and responsibilities C. Applications list and their details D. Backup and recovery procedures
Which of the following audit tools is MOST useful to an IS auditor when an audit trail is required? A. Integrated test facility (ITF) B. Continuous and intermittent simulation (CIS) C. Audit hooks D. Snapshots
Which of the following is an object-oriented technology characteristic that permits an enhanced degree of security over data? A. Inheritance B. Dynamic warehousing C. Encapsulation D. Polymorphism
An IS auditor should be concerned when a telecommunication analyst: A. monitors systems performance and tracks problems resulting from program changes. B. reviews network load requirements in terms of current and future transaction volumes. C. assesses the impact of the network load on terminal response times and network data transfer rates. D. recommends network balancing procedures and improvements.
Which of the following forms of evidence for the auditor would be considered the MOST reliable? A. An oral statement from the auditee B. The results of a test performed by an IS auditor C. An internally generated computer accounting report D. A confirmation letter received from an outside source