Which of the following techniques would provide the BEST
assurance that the estimate of program development effort is
reliable?
A. Function point analysis
B. Estimates by business area
C. A computer-based project schedule
D. An estimate by experienced programmer
Answer / guest
Answer: A
The use of estimation techniques, such as function point
analysis or lines of code estimation, provide a firm basis
for estimation, particularly if supported by historic
records of past activities. An estimate by an experienced
programmer would be the next best option. However, it may be
individualistic and unless there is a standard approach
adopted by the programmer, the estimate can vary
considerably from one programmer to another. Standard
project scheduling tools assist in working out the overall
project schedule, but are reliant on the quality of
estimation of individual tasks. They do not give an estimate
of actual development cost.
| Is This Answer Correct ? | 3 Yes | 0 No |
Which of the following BEST provides access control to payroll data being processed on a local server? A. Logging of access to personal information B. Separate password for sensitive transactions C. Software restricts access rules to authorized staff D. System access restricted to business hours
Functionality is a characteristic associated with evaluating the quality of software products throughout their lifecycle, and is BEST described as the set of attributes that bear on the: A. existence of a set of functions and their specified properties. B. ability of the software to be transferred from one environment to another. C. capability of software to maintain its level of performance under stated conditions. D. relationship between the performance of the software and the amount of resources used.
Following the development of an application system, it is determined that several design objectives have not been achieved. This is MOST likely to have been caused by: A. insufficient user involvement. B. early dismissal of the project manager. C. inadequate quality assurance (QA) tools. D. noncompliance with defined approval points.
To make an electronic funds transfer (EFT), one employee enters the amount field and another employee reenters the same data again, before the money is transferred. The control adopted by the organization in this case is: A. sequence check. B. key verification. C. check digit. D. completeness check.
Which of the following should be included in an organization's IS security policy? A. A list of key IT resources to be secured B. The basis for access authorization C. Identity of sensitive security features D. Relevant software security features
Responsibility and reporting lines cannot always be established when auditing automated systems since: A. diversified control makes ownership irrelevant. B. staff traditionally change jobs with greater frequency. C. ownership is difficult to establish where resources are shared. D. duties change frequently in the rapid development of technology.
In the development of an important application affecting the entire organization, which of the following would be the MOST appropriate project sponsor? A. The information systems manager B. A member of executive management C. An independent management consultant D. The manager of the key user department
When implementing an application software package, which of the following presents the GREATEST risk? A. Uncontrolled multiple software versions B. Source programs that are not synchronized with object code C. Incorrectly set parameters D. Programming errors
During an implementation review of a multiuser distributed application, the IS auditor finds minor weaknesses in three areas-the initial setting of parameters is improperly installed, weak passwords are being used and some vital reports are not being checked properly. While preparing the audit report, the IS auditor should: A. record the observations separately with the impact of each of them marked against each respective finding. B. advise the manager of probable risks without recording the observations, as the control weaknesses are minor ones. C. record the observations and the risk arising from the collective weaknesses. D. apprise the departmental heads concerned with each observation and properly document it in the report.
An IS auditor should be concerned when a telecommunication analyst: A. monitors systems performance and tracks problems resulting from program changes. B. reviews network load requirements in terms of current and future transaction volumes. C. assesses the impact of the network load on terminal response times and network data transfer rates. D. recommends network balancing procedures and improvements.
Which of the following is a control over database administration activities? A. A database checkpoint to restart processing after a system failure B. Database compression to reduce unused space C. Supervisory review of access logs D. Backup and recovery procedures to ensure database availability
Which of the following would allow a company to extend it?s enterprise?s intranet across the Internet to it?s business partners? A. Virtual private network B. Client-Server C. Dial-Up access D. Network service provider