Which of the following techniques would provide the BEST
assurance that the estimate of program development effort is
reliable?

A. Function point analysis

B. Estimates by business area

C. A computer-based project schedule

D. An estimate by experienced programmer

Answer Posted / guest

Answer: A

The use of estimation techniques, such as function point
analysis or lines of code estimation, provide a firm basis
for estimation, particularly if supported by historic
records of past activities. An estimate by an experienced
programmer would be the next best option. However, it may be
individualistic and unless there is a standard approach
adopted by the programmer, the estimate can vary
considerably from one programmer to another. Standard
project scheduling tools assist in working out the overall
project schedule, but are reliant on the quality of
estimation of individual tasks. They do not give an estimate
of actual development cost.

Is This Answer Correct ?    3 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

WHICH OF THE FOLLOWING IS OFTEN AN ADVANTAGE OF USING PROTOTYPING GOR DYDTEM DVELOPMENT

2842


purchase orders issued to vendors have been authorized as per the authorization matrix

1093