When a systems development life cycle (SDLC) methodology is
inadequate, the MOST serious immediate risk is that the new
system will:
A. be completed late.
B. exceed the cost estimates.
C. not meet business and user needs.
D. be incompatible with existing systems.
Answer / guest
Answer: C
Although all of the answers are risks of an inadequate SDLC
methodology, the first and most devastating is that the new
system will not need business and user needs and requirements.
| Is This Answer Correct ? | 10 Yes | 1 No |
An IS auditor, performing a review of an application?s controls, discovers a weakness in system software, which could materially impact the application. The IS auditor should: A. Disregard these control weaknesses as a system software review is beyond the scope of this review. B. Conduct a detailed system software review and report the control weaknesses. C. Include in the report a statement that the audit was limited to a review of the application?s controls. D. Review the system software controls as relevant and recommend a detailed system software review.
An IS auditor is reviewing the database administration function to ascertain whether adequate provision has been made for controlling data. The IS auditor should determine that the: A. function reports to data processing operations. B. responsibilities of the function are well defined. C. database administrator is a competent systems programmer. D. audit software has the capability of efficiently accessing the database.
Which of the following would be of the LEAST value to an IS auditor attempting to gain an understanding of an organization's IT process? A. IT planning documents with deliverables and performance results B. Policies and procedures relating to planning, managing, monitoring and reporting on performance C. Prior audit reports D. Reports of IT functional activities
An IS auditor performing a review of the IS department discovers that formal project approval procedures do not exist. In the absence of these procedures the IS manager has been arbitrarily approving projects that can be completed in a short duration and referring other more complicated projects to higher levels of management for approval. The IS auditor should recommend as a FIRST course of action that: A. users participate in the review and approval process. B. formal approval procedures be adopted and documented. C. projects be referred to appropriate levels of management for approval. D. the IS manager's job description be changed to include approval authority.
Which of the following is a practice that should be incorporated into the plan for testing disaster recovery procedures? A. Invite client participation. B. Involve all technical staff. C. Rotate recovery managers. D. Install locally stored backup.
An organization has an integrated development environment (IDE), where the program libraries reside on the server, but modification/development and testing are done from PC workstations. Which of the following would be a strength of an integrated development environment? A. Controls the proliferation of multiple versions of programs B. Expands the programming resources and aids available C. Increases program and processing integrity D. Prevents valid changes from being overwritten by other changes
The FIRST step in data classification is to: A. establish ownership. B. perform a criticality analysis. C. define access rules. D. create a data dictionary.
The risk that an IS auditor uses an inadequate test procedure and concludes that material errors do not exist when, in fact, they do, is an example of: A. inherent risk. B.control risk. C. detection risk. D. audit risk.
Change control procedures to prevent scope creep during an application development project should be defined during: A. design. B. feasibility. C. implementation. D. requirements definition.
In a risk-based audit approach, an IS auditor, in addition to risk, would be influenced by: A. the availability of CAATs. B. management's representation. C. organizational structure and job responsibilities. D. the existence of internal and operational controls
During a review of a business continuity plan, an IS auditor noticed that the point at which a situation is declared to be a crisis has not been defined. The MAJOR risk associated with this is that: A. assessment of the situation may be delayed. B. execution of the disaster recovery plan could be impacted. C. notification of the teams might not occur. D. potential crisis recognition might be delayed.
To review access to ceratin data base to determine whether the "new user" forms were correctly authorized. This is an example of: