what is entry and exit criteria?

Answers were Sorted based on User's Feedback



what is entry and exit criteria?..

Answer / mahesh

From my understanding:
Entry Criteria:

•Approved design and requirement documents.
•Test plan must be reviewed and signed off by TestLead/
Manager.
•All developed code must be unit tested. Unit and Link
testing must be completed and signed off by development
team.
•All human resources must be assigned and available with
the necessary Test bed.
•Application must be installed and configured similar to
the customer environment independently (segregated from
development environment) to start test execution.
•Test cases for Functional testing are created and reviewed.

Exit Criterai:

•All high priority defects must be fixed and re-tested.
•If any medium or low-priority defects are outstanding –
Project Manager must sign off the implementation risk as
acceptable.
•Test cases execution with test results.
•Bug Report.
•Test Report and Release approved by the Test Manager.
•Software Release Checklist

Is This Answer Correct ?    13 Yes 1 No

what is entry and exit criteria?..

Answer / @mit

In simple words,Entry & Exit criteria means of Start and
Stop point of any phase.Output of Entry criteria is the
Input of Exit criteria.

For Ex.
For Integration testing, the Entry and Exit criteria are as
follows:-
- All defetcs at Unit Testing are closed.
- Unit Test cases are uploaded in Defect Tracking tool.
- Test Scenairos provided by Developers(As per as company)
etc........

These are simple example of entry and Exit criteria.

Hope thats helps u all to undestand these terms easily.

Is This Answer Correct ?    1 Yes 0 No

what is entry and exit criteria?..

Answer / manish

Entry and exit criteria are a must for the success of any
project. If you do not know where to start and where to
finish then your goals are not clear. By defining exit and
entry criteria you define your boundaries. For instance, you
can define entry criteria that the customer should provide
the requirement document or acceptance plan. If this entry
criteria is not met then you will not start the project. On
the other end, you can also define exit criteria for your
project. For instance, one of the common exit criteria in
projects is that the customer has successfully executed the
acceptance test plan.

Is This Answer Correct ?    1 Yes 1 No

Post New Answer

More Manual Testing Interview Questions

On which order testing is done regression,retesting,functional,User Acceptance Testing,Usability Testing,Smoke Testing ???

1 Answers   Virtusa,


What is the diff. between Sanity , smoke and ad-hoc testing?

8 Answers  


What is the responsibility of programmers vs QA?

2 Answers   Crea, Pixel Byte,


What about the test case if the field only takes a certain number of characters or a minimum number?

0 Answers  


Where do you fit exactly?In automation or manual testing?

4 Answers   AppLabs,






what are things you want to check in web based testing?

3 Answers   CSS,


Who Prepare the Master Test Plan? Who Prepare the Test Plan?

1 Answers   Patni,


wat kinds of documents requied during regression testion ? at time regression testing is done? can we do it repeatdly

2 Answers  


What does FRS contain ?Explain in detail.

3 Answers  


Is quality control similar to quality assurance?

0 Answers  


1) In a software development project Spiral Model was Chosen as the development model. What is the best-suited reason for this? A)This model is the oldest and most widely used paradigm for software development. B)In this model users get the feel free the actual system and developers get to build something immediately. C)In this model risk analysis is done coupled with evolutionary S/W process model with the iterative nature of prototyping and controlled systematic aspects of water fall model D)This model combines elements of Classical model with this iterative philoophy of prototyping.

2 Answers   Mind Tree,


Hi, Can anyone suggest a test case writing technique for the below scenario. 1. User draws a lines on the image 2. User selects the lines and right clicks ( Measuremnts like distance between the start and the end point, coordinates of start point and coordinates of end point) 3. User selects one of the measurement Measurement is displayed

1 Answers   Siegeworks,


Categories