I. A code inspection is held for new code.
II. A code inspection is held for reused code.
III. A code inspection is held after the first compilation.
IV. A code inspection is held after the first error-free
compilation.

Which of the statements above are true of code
inspections?

1. I and IV
2. I, II, and IV
3. I, II, and III
4. II and IV
5. II and III



I. A code inspection is held for new code. II. A code inspection is held for reused code. III. A c..

Answer / shakthi

1. I and IV

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More QA Concepts Interview Questions

what is Test cases and test procedures.

2 Answers  


Formal Testing?

2 Answers  


Explain what is bug triage?

0 Answers  


WHAT IS ENTRY CRITERIA AND EXIT CRITERIA

6 Answers   HCL,


I test change password field for a application.But it accept new password same as old password. Is it not a issue??I raise this issue but developer team mark invalid.

2 Answers  






A power plant control system?

0 Answers  


what is web testing and what should you test in web testing?

2 Answers  


What tools are available to support testing during development of application?

0 Answers  


What is the difference between Test cases document and test cases design document?

0 Answers  


How u r estimating the budget 4 the project?

0 Answers   TCS, TFT,


what is test methodology? .What is its function in software testing? .What it discribe in test plan?

1 Answers  


We have one home page for a web application.It has so many components which are being tested by different teams. If one component testing get delayed but all other components testing is done, can we sign off testing for that home page? If no, what should be done?

0 Answers   Intuit,


Categories