Answer / guest
Suspension/Resumption Criteria in a Software Test Plan :
If any defects are found which seriously impact the test
progress the test lead may choose to supend testing.
The criteria which are considered for suspension or
resumption are :
[a] hardware / software not available at the time indicated
in the project schedule
[b] the build contians many serious defects which seriously
prevent or limit testing progress
[c] Assigned test resources are not available when needed
by the test team
Resumption Criteria :
If testing is suspended, resumption will only occur when
the problem(s) that caused the suspension have been
resolved. When a critical defect is the cause of the
suspension, the “FIX” must be verified by the testing team
before testing is resumed
please correct me if iam wrong
| Is This Answer Correct ? | 36 Yes | 5 No |
Answer / sonia janet
Suspension Criteria in a Software Test Plan :
In case of any serious issues are found during the QA the
testing is suspended by the QA member in absence of higher
QA people. And that is documented in the test plan for the
official purpose.
Resumption Criteria in a Software Test Plan
The issue that caused the suspension should be resolved and
documented in the test plan for the official purpose.The
issue must be re validated by the QA member.
Every QA process should be documented.That will help to
ensure the QA .
If any one of you have any different opinion please post
your reply.
| Is This Answer Correct ? | 4 Yes | 3 No |
what is meant by support project in testing?
what is test phase?i want answer any body give me answer pls
What is Software Testing? Objectives of Testing?
On what basis you are fixing up the time for project completion?
How to test an Scheduled event? For ex: in an investment banking application, the scheduler will create an equity anbd user has nothing to do but tester has to test if the instrument is created properly or not?
What is smoke testing and when it will be done?
What is Conventional & Unconventional testing?
How to do manual testing of a E-insurance project (end to end process)
What's the difference between System testing and Performance testing?
Artifacts in design phase of SDLC ?
if bug is found & we will know the main Resion for that bug Arrise 1 - Corrective & Prevention Action 2 - Risk ana 3 - Root Cause analysis 4 - Impact analysis
what are the different banking terms used in your project?like new acc,dormate,active accounts....