Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


what r the key components in a test plan document?

Answers were Sorted based on User's Feedback



what r the key components in a test plan document?..

Answer / saikrishna reddy.k

following are thekey components in test plan
1.introduction
2.scope&objective
3.testplan id
4.list of features
4.1features to tested
4.2features not to tested
5.test approach
6.test environment
7.entry criteria
8.suspention criteria
9.exit criteria
10.test deliverables
11.staffing needs
12.roles and resposibilities
13.training needs
14.communication & status reporting
15.schudule
16.approvals
if any thing is more pls give me feed back.
thank you.

Is This Answer Correct ?    5 Yes 0 No

what r the key components in a test plan document?..

Answer / suneel reddy

key components are

The extent to which

features tobe tested

features not to be tested

Feature pass/fail
test envirornment
testing approach
suspension criteria

Is This Answer Correct ?    1 Yes 0 No

what r the key components in a test plan document?..

Answer / surya

14.communication & status reporting
will not come under Test Plan as per IEEE 829 standard.

Is This Answer Correct ?    2 Yes 1 No

what r the key components in a test plan document?..

Answer / prajakta

Along with above some others are there
1) Risk
2) Test Schedule
3)Control Procesure like bug Review meeting, change request,
defect reporting.

Is This Answer Correct ?    0 Yes 0 No

what r the key components in a test plan document?..

Answer / prajakta

Along with above some others are there
1) Risk
2) Test Schedule
3)Control Procesure like bug Review meeting, change request,
defect reporting.

Is This Answer Correct ?    0 Yes 0 No

what r the key components in a test plan document?..

Answer / chandru

In addition to the above components the factors like:

1.Unforeseen problems that means we have to guess certain
problems that may arise in client's place.
2.Scheduling and allocation the testing resources
3. HW/SW requirement.
4.In additon to Risks, failures to be identified like HDD
crash, DB recovery, back ups needed in terms of HW/SW and
resources to be planned in advance!

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More QA Concepts Interview Questions

I'm looking for a latest news on software testing, please help me.

1 Answers  


How is retesting different from regression testing?

0 Answers  


what is Installation Testing?

6 Answers  


What do you like most about Quality Assurance/Testing?

0 Answers  


in v model of software testing which processes comes under QA and which processes comes under QC?And what is verification and validation please anwer these question i realy very confused

9 Answers   KPIT,


create a daily status report or list the items you will cover in a status report

0 Answers   QA, TCS,


How to test and to get the difference between two images which is in the same window?

0 Answers  


what is the SOAP UI and Web services? what are the uses in testing?

0 Answers   IBM,


List out various tools required to support testing during development of the application?

0 Answers  


Describe the benefits of agile testing.

0 Answers  


how to identify metrics, integrity level, identify risks and identify security issues in ieee 829 standard explain with examples??

0 Answers  


What is the procedure for acquiring CMMI Certification for the company Is CMM no longer used

2 Answers  


Categories