Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


You are a project manager working on contract. You’ve performed earned value analysis and discovered that the project will be completed on time and under the original estimated amount. This means the profit to your company will decrease as will your personal bonus. Which of the following should you do?
A. Add activities to the project to increase the cost enough to meet the original estimated amount.
B. Tell the customer you're adding additional requirements to the project chat were originally cut because of cost constraints.
C. Inform the customer that the project is completed and has come in under budget.
D. Bill the customer for the full amount of the contract as this was the original agreed-upon price.


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

Which of the following processes are performed in the Closing process group and in what order? A. Administrative Closure then Contract Closeout B. Scope Verification then Administrative Closure C. Contract Closeout then Scope Verification D. Contract Closeout then Administrative Closure

0 Answers  


How do you set goals for your team? And how do you track these goals?

0 Answers  


All of the following are tools and techniques of the Schedule Development process except? A. CPM B. RAM C. GERT D. PERT

0 Answers  


Which of the following tools and techniques shows the impacts of one decision over another as well as the probability and cost of each risk along a logical path? A. Simulation B. Decision tree C. Probability/impact risk matrix D. Sensitivity analysis

0 Answers  


The project schedule is used to determine all of the following except: A. Cost estimates B. Activity start dates C. Float times D. Activity end dates

0 Answers  


Describe size oriented metrics.

0 Answers  


Your team is split between two buildings on either side of town. As a result, the team isn't very cohesive because the members don't know each other very well. The team is still in the storming stage because of the separation issues. Which of the following should you consider? A. Corrective action B. Collocation C. Training D. Conflict resolution

0 Answers  


You are the project manager for Heartthrobs by the Numbers Dating Services. You’re working on an updated Internet site that will display pictures as well as short bios of prospective heartbreakers. You have your activity list and resource requirements in hand and are planning on using qualitatively based durations and reserve time to determine activity durations. Which of the following is true? A. You are using inputs of the Activity Duration Estimating process. B. You are using tools and techniques of the Cost Estimating process. C. You are using tools and techniques of the Activity Duration Estimating process. D. You are using inputs of the Cost Estimating process.

0 Answers  


All of the following describe the activity list except: A. It's an extension of the WBS. B. It includes all activities of the project. C. It describes the WBS updates. D. It includes a description of project activities.

0 Answers  


You are project manager for an engineering company. Your company won the bid to add ramp-metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor's work involves digging the holes and setting the lamp poles in concrete. The subcontractor's performance is not meeting the contract requirements. All of the following are valid options except: A. You document the poor performance in written form and send the correspondence to the subcontractor change request through Contract Administration. B. You terminate the contract for poor performance and submit a change request through Contract Administration. C. You submit a change request through Contract Administration to ask the subcontractor to comply with the terms of the contract. D. You agree to meet with the subcontractor to see if a satisfactory solution can be reached.

0 Answers  


Your selection committee is debating between two projects. Project A has a payback period of 18 months. Project B has a cost of $125,000 with expected cash inflows of $50,000 the first year and $25,000 per quarter after that. Which project should you recommend? A. Either Project A or Project B because the payback periods are equal B. Project A because Project B's payback period is 21 months C. Project A because Project B's payback period is 24 months D. Project A because Project B's payback period is 20 months

0 Answers  


You are the project manager for a large construction project. The project objective is to construct a set of outbuildings to house the Olympic support team that will be arriving in your city 18 months from the project start date. Resources are not readily available as they are currently assigned to other projects. Jack, an expert crane operator, is needed for this project two months from today. Which of the following skills will you use to get Jack assigned to your project? A. Negotiation and influencing skills B. Communication and organizational skills C. Communication skills D. Problem-solving skills

0 Answers  


Categories