What are the different software reengineering activities?


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

You are a project manager working for Mail House King. Your company processes orders for several mail-order catalog companies. Your project is to install new mail-sorting equipment and software. You’ve had some problems and experienced some variances so far during the project. You do not expect these variances to continue, as they're atypical. Your project sponsor has asked for an EAC. You know the following information: PV = 800, BAC = 700, EV = 675, AC = 750, and ETC = 30. Which of the following is the correct EAC given the circumstances? A. 25 B. 760 C. 775 D. 833

0 Answers  


You are project manager for a nonprofit organization. Your project has come about due to a social need. Your sponsor wants to get right to the Planning process. However, you know that a project charter should be published prior to proceeding to the Planning processes. All of the following are true regarding project charters except: A. Project charters always include cost and time estimates. B. Project charters always include the product description and business need for the product. C. Project charters recognize and acknowledge the existence of the project. D. Project charters commit organizational resources to the project.

0 Answers  


Which performance measurement tells us what the projected total cost of the project will be at completion? A. ETC B. CPI C. SPI D. EAC

0 Answers  


How do you set goals for your team?

0 Answers  


Which of the following is true? A. Discounted cash flow analysis is the least precise of the cash flow techniques as it does not consider the time value of money. B. NPV is the least precise of the cash flow analysis techniques as it assumes reinvestment at the discount rate. C. Payback period is the least precise of the cash flow analysis techniques as it does not consider the time value of money. D. IRR is the least precise of the cash flow analysis techniques because it assumes reinvestment at the cost of capital.

0 Answers  






During your project meeting, a problem was discussed and a resolution to the problem was reached. During the meeting, the participants started wondering why they thought the problem was such a big issue. Sometime after the meeting, you received and e-mail from one of the meeting members saying they've changed their mind about the solution reached in the meeting and need to resurface the problem. The solution reached during the initial project meeting is an example of which of the following conflict resolution techniques? A. Confrontation B. Forcing C. Smoothing D. Storming

0 Answers  


How to track your team members?

0 Answers  


You've constructed the WBS for your recent project. Level two assignments have been made, and you've requested that the sub project manager’s report back to you in 3 weeks with each of their individual WBS constructed. All of the following are true except: A. The work package level facilitates resource assignments. B. The work package level is the lowest level in the WBS. C. The work package level defines the agreed-upon deliverables. D. The work package level facilitates cost and time estimates. ?

0 Answers  


You are the project manager for Zippy Tees. Your company has decided to outsource the manufacturing of miniature bears to be attached to your trendy T-shirts. Which of the following is true? A. A good product description is all that's required. The project manager will supply this to the vendor. B. The contract can serve as the project charter. The product description will be included in the contract. C. The project manager should write the project charter because the project manager will be managing the vendor portion of this project as well. D. The vendor should write the project charter as they are responsible for manufacturing the bears.

0 Answers  


What are the triple constraints? A. Time, schedules, and quality B. Time, availability, and quality C. Time, money, and schedules D. Time, money, and quality

0 Answers  


Which of the following is true regarding IRR? A. IRR assumes reinvestment at the cost of capital. B. IRR is the discount rate when NPV is greater than zero. C. IRR is a constrained optimization method. D. IRR is the discount rate when NPV is equal to zero. ?

0 Answers  


Your project sponsor has requested a cost estimate for the project you're working on. This project is similar in scope to a project you worked on last year. She would like to get the cost estimates as soon as possible. Accuracy is not her primary concern right now. She needs a ball park figure by tomorrow. You decide to use: A. Analogous estimating techniques B. Bottom-up estimating techniques C. Parametric modeling techniques D. Computerized modeling techniques

0 Answers  


Categories