You are a project manager for Cinema Snicker Productions. Your company specializes in producing comedy films for the big screen. Your latest project has just been completed and accepted. You've been given your next project, which starts right away. Which of the following is true?
A. This project ended due to extinction because it was completed and accepted.
B. This project ended due to integration because it was completed and accepted and the project manager moved on to a new project.
C. This project ended due to addition because it was completed and accepted and archived into the company's catalog of available films.
D. This project ended due to integration because it was completed and accepted.
No Answer is Posted For this Question
Be the First to Post Answer
You are a project manager for Dutch Harbor Consulting. Your latest project involved the upgrade of an organization's operating system on 236 servers. You performed this project under contract. You are in the Contract Closeout process and know that you should document: A. Lessons learned B. Performance measurements C. Formal acceptance D. Product verification
Project selection criteria might include: A. Benefit measurement methods B. Constrained optimization analysis C. NPV calculations D. Potential market share or increased public perception
What are the outputs of the Team Development process? A. Performance improvements, input to performance appraisals B. Input to performance appraisals, reward and recognition systems C. Performance improvements, input to performance appraisals, performance reports D. Work results, input to performance appraisals, performance reports
You are a project manager responsible for the construction of a new office complex. You are taking over for a project manager who recently left the company. The prior project manager completed the scope statement and scope management plan for this project. In your interviews with some key stakeholders, you conclude which of the following? A. They understand that the scope statement assesses the Stability of the project scope and outlines how to incorporate scope changes into the project. B. They understand that the scope management plan assesses the stability of the project scope and outlines how to incorporate scope changes into the project. C. They understand that the scope management plan is deliverables oriented and cost estimates can be easily derived it. D. They understand that the scope statement is deliverables oriented and cost estimates can be easily derived from it.
How to track your team members?
You are the project manager for Heart of Texas casual clothing company. They're introducing a new line of clothing called Black Sheep Ranch Wear. You will outsource the production of this clothing line to a vendor. The vendor has requested a SOW. All of the following are true except: A. The SOW contains a description of the new clothing line. B. As the purchaser, you are required to write the SOW. C. The SOW contains the objectives of the project. D. The vendor requires a SOW to determine if they can produce the clothing line given the very detailed specifications of this project.
you are the project manager of a project , customer is asking for a change in scope and agrees that it will be a CR. But you do not want to take the CR for whatever reason. How will you convince the customer in doing so
You are a project manager for Snow Fun, a chain of retail shops specializing in winter sports gear and clothing. You’ve been working on contract with Snow Fun and are ready to move on to your next assignment. The customer has signed off on the project, formal acceptance notices have been distributed, and project closure procedures have been performed. What type of project ending is this? A. Extinction B. Starvation C. Integration D. Addition
You are project manager for an engineering company. Your company won the bid to add ramp-metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor's work involves digging the holes and setting the lamp poles in concrete. The subcontractor's performance is not meeting the contract requirements. All of the following are valid options except: A. You document the poor performance in written form and send the correspondence to the subcontractor change request through Contract Administration. B. You terminate the contract for poor performance and submit a change request through Contract Administration. C. You submit a change request through Contract Administration to ask the subcontractor to comply with the terms of the contract. D. You agree to meet with the subcontractor to see if a satisfactory solution can be reached.
All of the following are benefits of meeting quality requirements except: A. An increase in stakeholder satisfaction B. Less rework C. Low turnover D. Higher productivity
You know that PV = 475, AC = 430, EV = 480, EAC = 40, and BAC = 525. What is VAC? A. 440 B. 390 C. 485 D. 435
You are a project manager who believes people will always perform at their best if given the proper expectations and motivation. Which theory do you subscribe to? A. Theory X B. Hygiene theory C. Contingency theory D. Theory Y