Each of the following describes an element of the Scope Definition process except:
A. Breaking down the major deliverables of the project into smaller, manageable components
B. Supporting detail
C. Decomposition
D. Improving the accuracy of time and cost estimates
No Answer is Posted For this Question
Be the First to Post Answer
Describe the risk in software engineering.
You are a project manager for Picture Shades, Inc. They manufacture window shades for hotel chains that have replicas of Renaissance-era paintings on the inside of the shades. Picture Shades is taking their product to the home market, and you're managing the new project. They will offer their products at retail stores as well as on their website. You're developing the project schedule for this undertaking and have determined the critical path. Which of the following is true? A. You calculated the most likely start date and most likely finish dates, float time, and weighted average estimates. B. You calculated the activity dependency, and the optimistic and pessimistic activity duration estimates. C. You calculated the early and late start dates, early and late finish dates, and float times for all activities. D. You calculated the optimistic, pessimistic, and most likely duration times and the float times for all activities.
How project comes to a software company? what is the role of sales department,marketing department,delivery manager,project manager in a software development? simply,what is project life cycle?
You have been asked to submit a proposal for a project that has been put out for bid. First, you attend the bidders conference to ask questions of the buyers and to hear the questions some of the other bidders will ask. Which of the following is true? A. Bidders conferences are a tool and technique of the Source Selection process. B. Bidders conferences are an output of the Source Selection process. C. Bidders conferences are an output of the Solicitation process. D. Bidders conferences are a tool and technique of the Solicitation process.
You are the project manager for Heartthrobs by the Numbers Dating Services. You’re working on an updated Internet site that will display pictures as well as short bios of prospective heartbreakers. You have your activity list and resource requirements in hand and are planning on using qualitatively based durations and reserve time to determine activity durations. Which of the following is true? A. You are using inputs of the Activity Duration Estimating process. B. You are using tools and techniques of the Cost Estimating process. C. You are using tools and techniques of the Activity Duration Estimating process. D. You are using inputs of the Cost Estimating process.
What is the meaning of scope of the project?
Which of the following is true? A. Discounted cash flow analysis is the least precise of the cash flow techniques as it does not consider the time value of money. B. NPV is the least precise of the cash flow analysis techniques as it assumes reinvestment at the discount rate. C. Payback period is the least precise of the cash flow analysis techniques as it does not consider the time value of money. D. IRR is the least precise of the cash flow analysis techniques because it assumes reinvestment at the cost of capital.
Which of the following describes the cost of quality associated with scrapping, rework, and downtime? A. Internal failure costs B. External failure costs C. Prevention costs D. Appraisal costs
Your team is split between two buildings on either side of town. As a result, the team isn't very cohesive because the members don't know each other very well. The team is still in the storming stage because of the separation issues. Which of the following should you consider? A. Corrective action B. Collocation C. Training D. Conflict resolution
Which of the following is constraint chat you might find during the Organizational Planning process? A. Organizational structure, expected staff assignments, collective bargaining agreements, and project management team preferences B. Organizational structure, organizational interfaces, technical interfaces, and interpersonal interfaces C. Organizational interfaces, expected staff assignments, collective bargaining agreements, and project management team preferences D. Organizational interfaces, technical interfaces, and interpersonal interfaces
You are a project manager for Waterways Houseboats, Inc. You have been asked to perform a benefit/cost analysis for two proposed projects. Project A costs $2.4 million with potential benefits of $12 million and future operating cost of $3 million. Project B costs $2.8 million with potential benefits of $14 million and future operating costs of $2 million. Which project should you recommend? A. Project A because the cost to implement is cheaper than Project B B. Project A because the potential benefits plus the future operating costs are less in value than the same calculation for Project B C. Project B because the potential benefits minus the implementation and future operating costs are greater in value than the same calculation for Project A D. Project B because the potential benefits minus the costs to implement are greater in value than the same calculation for Project A
What limits the options of the project team? A. Technology B. Constraints C. Deliverables D. Assumptions