Each of the following describes an element of the Scope Definition process except:
A. Breaking down the major deliverables of the project into smaller, manageable components
B. Supporting detail
C. Decomposition
D. Improving the accuracy of time and cost estimates


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

Your organization regularly uses a tool and technique of the Contract Closeout process to identify lessons learned, including the successes and failures, which will benefit future activity on this project and on future projects. Which tool and technique arc they using? A. Product documentation inspection B. Contract process review C. Performance measurement review D. Procurement audit

0 Answers  


You are a project manager for Fountain of Youth Spring Water bottlers. You are installing a new accounting system and have identified several problems and their causes. You decide to use which of the following flowcharts to diagram the problems' causes and effects? A. Decision tree diagram B. Fishbone diagram C. Benchmark diagram D. Simulation tree diagram

0 Answers  


You are the project manager for Changing Tides video games. You have produced a project network diagram and have updated the activity list. Which process have you just finished? A. The Activity Sequencing process, which identifies all the specific activities of the project B. The Activity Sequencing process, which identifies all the activity dependencies C. The Activity Duration Estimating process, which diagrams project network time estimates D. The Activity Duration Estimating process, which identifies all the dependent activities of the project

0 Answers  


You are a project manager for a growing dairy farm. They offer their organic dairy products regionally and are expanding their operations to the West Coast. They're in the process of purchasing and leasing dairy farms to get operations under way. The sub project manager in charge of network operations has reported some hardware problems to you. You’re also having some other coordinating and integrating other elements of the project. Which of the following is true? A. You are in the Project Plan Execution process. B. Your project team doesn't appear to have the right skills and knowledge needed to perform this project. C. You are in the Information Distribution process. D. Your project team could benefit from some team-building exercises.

0 Answers  


Each of the following is true regarding the risk management plan except: A. The risk management plan is an output of the Risk Management Planning process B. The risk management plan includes a description of the responses to risks and triggers. C. The risk management plan includes thresholds, scoring and interpretation methods, responsible parties, and budgets. D. The risk management plan is an input to all the remaining risk planning processes.

0 Answers  






You've constructed the WBS for your recent project. Level two assignments have been made, and you've requested that the sub project manager’s report back to you in 3 weeks with each of their individual WBS constructed. All of the following are true except: A. The work package level facilitates resource assignments. B. The work package level is the lowest level in the WBS. C. The work package level defines the agreed-upon deliverables. D. The work package level facilitates cost and time estimates. ?

0 Answers  


How do you manage team performance?

0 Answers  


What is the w5hh (wwwwwhh) principle given by barry boehm?

0 Answers  


Your project's primary constraint is quality. In order to make certain the project team members don't feel too pressed for time and to avoid schedule risk, you decide to use which of the following activity estimating tools? A. Expert judgment B. Quantitatively based durations C. Reserve time D. Analogous estimating

0 Answers  


You are the project manager for BB Tops, a nationwide toy store chain. You are working on estimates for your latest project and have gathered several variables for your model. You've determined the following: A. Parametric modeling is a top-down technique that uses variables to produce time estimates. B. Parametric modeling is a mathematical formula that uses variables to produce cost estimates. C. Contingency estimating is a top-down technique that uses variables to produce cost estimates. D. Contingency estimating is a mathematical model that uses variables to produce time estimates.

0 Answers  


The purpose of a quality audit includes all of the following except: A. Examines the work of the project and formally accepts the work results B. Determines how the project is progressing and makes corrections C. Identifies lessons learned D. Reviews quality management activities to ensure the right quality elements are being examined

0 Answers  


How do you communicate bad news in your team?

0 Answers  


Categories