You've constructed the WBS for your recent project. Level two assignments have been made, and you've requested that the sub project manager’s report back to you in 3 weeks with each of their individual WBS constructed. All of the following are true except:
A. The work package level facilitates resource assignments.
B. The work package level is the lowest level in the WBS.
C. The work package level defines the agreed-upon deliverables.
D. The work package level facilitates cost and time estimates. ?


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

What are decision models? A. Project selection criteria B. Project selection methods C. Project selection committees D. Project resource and budget selection criteria

0 Answers  


You are the project manager for a construction company that is building a new city and county office building in your city. You recently looked over the construction site to determine if the work to date was conforming to the requirements and quality standards. Which tool and technique of Quality Control are you using? A. Performance measurements B. Inspection C. Sampling D. Prevention

0 Answers  


Lessons learned are used for all of the following except: A. To provide historical information that you can review during your next project B. To document employee performance C. To identify successes and failures on the project D. To record the causes of performance variances

0 Answers  


You've constructed the WBS for your recent project. Level two assignments have been made, and you've requested that the sub project manager’s report back to you in 3 weeks with each of their individual WBS constructed. All of the following are true except: A. The work package level facilitates resource assignments. B. The work package level is the lowest level in the WBS. C. The work package level defines the agreed-upon deliverables. D. The work package level facilitates cost and time estimates. ?

0 Answers  


You are working on a project that is similar in scope to a project performed last year by your company. You might consider which of the following? A. Using the previous project's alternatives identification as a template B. Reusing the previous project's benefit/cost analysis as justification for this project C. Using the previous project's WBS as a template D. Reusing the previous project's product description when writing the scope statement

0 Answers  






You are a project manager for a network cabling project for your organization. Your project team is made up of six full-time employees and three contractors. This is the first time they have all worked together. You know that the team will go through the stages of team development in the following order: A. Forming, storming, norming, and performing B. Storming, norming, forming, and performing C. Norming, storming, forming, and performing D. Forming, norming, storming, performing

0 Answers  


what is software project planning?

0 Answers  


The project schedule is used to determine all of the following except: A. Cost estimates B. Activity start dates C. Float times D. Activity end dates

0 Answers  


All of the following are true regarding the ADM method except: A. It's a tool and technique of Activity Sequencing. B. It uses one time estimate to determine durations. C. It's also called AOA. D. It's rarely used today.

0 Answers  


A project is considered successful when: A. The product of the project has been manufactured. B. The project sponsor announces the completion of the project. C. The product of the project is turned over to the operations area to handle the ongoing aspects of the project. D. The project meets or exceeds the expectations of the stakeholders.

0 Answers  


You are working on a project that will upgrade the phone system in your customer service center. You have used bottom-up estimating techniques to assign costs to the project activities and have determined the cost baseline. Which of the following is true? A. You have completed the Cost Estimating process and now need to complete the Cost Budgeting process to determine the project's baseline. B. You have completed the Project Plan Development process and established a project baseline to measure future project performance against. C. You have completed the Cost Estimating process and now need to complete the Project Plan Development process to establish a project baseline to measure future project performance against. D. You have completed the Cost Budgeting process, and the cost baseline will be used to measure future project performance.

0 Answers  


You are a project manager for an agricultural supply company. You have just completed and obtained sign-off on the scope statement for your new Natural Bug Busters project. A key stakeholder has informed you that a deliverable is missing from the scope statement. This deliverable is a critical success factor. You should do which of the following? A. Inform the stakeholder that work not stated in the scope statement is excluded from the project. B. Modify the scope statement to reflect the new deliverable. C. Inform the stakeholder that this deliverable can be included in the next project since sign-off has already been obtained. D. Modify the scope statement after an approved change request has been received from the stakeholder.

0 Answers  


Categories