Which of the following is true regarding NPV?
A. NPV assumes reinvestment at the cost of capital.
B. NPV decisions should be made based on the highest value for all of the selections.
C. NPV assumes reinvestment at the prevailing rate.
D.NPV assumes reinvestment at the NPV rate.
No Answer is Posted For this Question
Be the First to Post Answer
How do you start a project plan?
The Critical Path Method is a mathematical tool and technique of the Schedule Development process. All of the following are true regarding CPM except: A. Determines a single early and late start date and a single early and late finish date B. Calculates expected value C. Focuses on the calculation of float time D. Shows the critical path, or the path with the longest duration
Your hardware vendor left you voicemail saying that a potential snowstorm in the Midwest might prevent your equipment from arriving on time. She wanted to give you a heads-up and asked that you return the call. Which of the following is true? A. This is a secondary risk, which is an output of Risk Response Planning. B. This is a contingency plan, which is an output of Risk Response Planning. C. This is a risk, which is an output of Risk Identification. D. This is a trigger, which is an output of Risk Identification.
How does a project manager can avoid the above given ten points for the success of project.
You are the project manager for a cable service provider. Your team members are amiable with each other and are careful to make project decisions jointly. Which of the following is true? A. They are in the smoothing stage of Team Development. B. They are in the norming stage of Team Development. C. They are in the forming stage of Team Development. D. They are in the forcing stage of Team Development.
Which of the following is true regarding the scope statement? A. It describes how to make changes to project scope. B. It describes project deliverables and serves as a baseline for future project decisions. C. It assesses the stability of the project scope and is a baseline for future project decisions. D. It assesses the reliability of the project scope and describes the frequency of changes and their impacts.
The VP of customer service has expressed concern over a project you're involved in. His specific concern is that if the project is implemented as planned, he’ll have to purchase additional equipment to staff his customer service center. The cost is substantial and was not taken into consideration in the project budget. The project sponsor insists that the project must go forward as originally planned or the customer will suffer. Which of the following is true? A. The VP of customer service is correct. Since the cost was not taken into account at the beginning of the project, the project should not go forward as planned. Project initiation should he revisited to examine the project plan and determine how changes can be made to accommodate customer service. B. The conflict should be resolved in favor of the customer. C. The conflict should be resolved in favor of the project sponsor. D. The conflict should be resolved in favor of the VP of customer service.
What are the 10 knowledge areas of project management?
As a PMP, you will be required to comply with the Project Management Professional Code of Professional Conduct. This code refers to all of the following except: A. Reporting conflicts of interest B. Reporting experience and PMP status truthfully C. Complying with stakeholder requirements D. Complying with rules and policies of foreign countries
PERT is: A. The longest path B. A weighted average technique C. A simulation technique D. Widely used in practice to determine schedule durations
You are a project manager working for Mail House King. Your company processes orders for several mail-order catalog companies. Your project is to install new mail-sorting equipment and software. You’ve had some problems and experienced some variances so far during the project. Your project sponsor has asked for an EAC. You know the following information: PV = 800, BAC = 700, EV = 675, AC = 750, and ETC = 30. Which of the following is the correct EAC given the circumstances? A. 778 B. 780 C. 861 D. 833
What will you do, if your subordinate has a problem with you? How will you deal with this situation