Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


entry criteria and exit criteria for unit testing, integration
testing, system testing and uat



entry criteria and exit criteria for unit testing, integration testing, system testing and uat..

Answer / neethu sebastian

Entry criteria for unit test
1.) All the requirement and documents are reviewed, finalized and approved.
2.) Application development should be completed
3.) Test environment is ready
4.) UnitTest Framework must be ready (in case of automated unit testing)
5.) Unit testing tools like Rational Software, JavaScript Assertion Unit, CUT, Dotunit ...etc (if tools are using) must be installed and configured.
(** last 2 points are optional hence can be avoided in interviews)

Exit criteria for Unit testing
1.) All the Unit test cases are executed.
2.) All the defects are resolved.
3.) coding is completed
4.) Code optimization (removal of redundant code, labeling of codes, removal of unused labels, removal of warning ..etc) is completed.

Entry criteria for integration testing
1.) Unit test exit criteria must meet
2.) Test environment should be ready
3.) Integration plan should be ready.
4.) Each module must gone through unit testing before the integration process.

Exit Criteria for Integration testing
1.) Successful execution of the integration tests.
2.) All priority bugs are resolve and closed.


Entry criteria for System testing
1.) Successful completion of integration testing process.
2.) Priority bugs found during integration testing must be fixed and closed.
3.) System testing environment must be available.
4.) Test cases must be available to execute

Exit Criteria for system testing
1.) Successful execution of the system tests.
2.) All specified business and functional requirements must be met.
3.) Priority bugs have been fixed and closed.
4.) Systems compatibility must be tested on various platforms

Entry Criteria for acceptance testing
1.) Successful completion of system testing phase.
2.) Priority bugs found during previous testing activities must be fixed and closed.
3.) Functional and Business requirement must be met.
4.) Acceptance testing environment should be ready.
5.) Test cases must be available.

Exit Criteria of Acceptance testing
1.) Successful execution of the user acceptance tests.
2.) approval for test Closure
3.)All Business requirements must be fulfilled.
4.) No critical defects are left out.

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Manual Testing Interview Questions

when we swipe the credit card what will genertaed in Back end. how system will validated from the back end for credit card who is Aquriree and Issuer ,

1 Answers   MetLife, Quark,


Please provide the examples for following scenarios 1.High Sevierity Low Priority 2.Low Sevierity High priority

4 Answers  


when you open a stand alone application then the application is displayed on the screen.what type of testing is this?

1 Answers  


What is exploratory testing and when should it be performed?

0 Answers  


difference between smoke testing and sanity testing?

4 Answers   Mastek,


what type of bugs u found commonly in ur project?

3 Answers   Wipro,


can any one please give bug reporting format of bugzilla ?

3 Answers   Syntel,


How you convine the Client that the application is very stable after testing. What type of Document you show to him or anything.

3 Answers   HP,


When should testing start in a project?

7 Answers   TCS,


Write testcase for delete functionality?

1 Answers   IBIT PU,


hi this is chik here iam showing my current project ERP and am prepair in hr model please tell me details about it and what all function test in hr model and give me some test caserelated to this module.Please tell me am faceing lots of problem in interview am not able to explain in interview please help me out my id is chiku_69@yahoo.in

0 Answers  


What is configuration management in software testing ?

2 Answers  


Categories