what is entry and exit criteria?

Answers were Sorted based on User's Feedback



what is entry and exit criteria?..

Answer / mahesh

From my understanding:
Entry Criteria:

•Approved design and requirement documents.
•Test plan must be reviewed and signed off by TestLead/
Manager.
•All developed code must be unit tested. Unit and Link
testing must be completed and signed off by development
team.
•All human resources must be assigned and available with
the necessary Test bed.
•Application must be installed and configured similar to
the customer environment independently (segregated from
development environment) to start test execution.
•Test cases for Functional testing are created and reviewed.

Exit Criterai:

•All high priority defects must be fixed and re-tested.
•If any medium or low-priority defects are outstanding –
Project Manager must sign off the implementation risk as
acceptable.
•Test cases execution with test results.
•Bug Report.
•Test Report and Release approved by the Test Manager.
•Software Release Checklist

Is This Answer Correct ?    13 Yes 1 No

what is entry and exit criteria?..

Answer / @mit

In simple words,Entry & Exit criteria means of Start and
Stop point of any phase.Output of Entry criteria is the
Input of Exit criteria.

For Ex.
For Integration testing, the Entry and Exit criteria are as
follows:-
- All defetcs at Unit Testing are closed.
- Unit Test cases are uploaded in Defect Tracking tool.
- Test Scenairos provided by Developers(As per as company)
etc........

These are simple example of entry and Exit criteria.

Hope thats helps u all to undestand these terms easily.

Is This Answer Correct ?    1 Yes 0 No

what is entry and exit criteria?..

Answer / manish

Entry and exit criteria are a must for the success of any
project. If you do not know where to start and where to
finish then your goals are not clear. By defining exit and
entry criteria you define your boundaries. For instance, you
can define entry criteria that the customer should provide
the requirement document or acceptance plan. If this entry
criteria is not met then you will not start the project. On
the other end, you can also define exit criteria for your
project. For instance, one of the common exit criteria in
projects is that the customer has successfully executed the
acceptance test plan.

Is This Answer Correct ?    1 Yes 1 No

Post New Answer

More Manual Testing Interview Questions

What is TEST PLAN, TEST STRATEGY, TEST SCENARIO, TEST CASE, TEST SCRIPT? can any body give me definition with example.

1 Answers  


Generally Where do we concentrate more on the web based applications testing....fox ex: security testing, performance testing etc....

2 Answers   Symphony,


Can anyone list out major scenarios for an application managing drug composition?

0 Answers  


What is the difference between Use Case and test case?

4 Answers  


in sdlc process what is the rool of PM,TL,DEVELOPER,tester in each and every phase? pelese explain me in detail?

2 Answers  






Which website will help me to get all manual interview questions at one place

1 Answers   Satyam,


What is Bug Validation? What can be a different resultant after the same?

3 Answers   Satyam,


how to find the bugs and log the test cases?

6 Answers   Mastek,


What should be a cover letter name while updating resume on naukri.com? please post answer

1 Answers  


What happens if we access a website that has cookies once the browser cookies are disabled?Does the website will be accessed?Though accessed, does the session will be tracked?

1 Answers  


can anyone suggest the website which gives detailed informtion on configuration mnagement tools VSS?

0 Answers  


WHAT IS ROLE OF TESTER IN TEST PLANNING?

5 Answers  


Categories