In cement concrete how to check a quality of material also proportion of material at site ?
NTPC,
1439In the different classes or grades of concrete, what is the difference between C20, M20 B20. what are the letters C, M, and B stands for.
3718How much depth of excavation have to do for Highrised builldings?if Raft foundation how much,and Pile foundation how much?
GMR,
1 2817Post New Civil Engineering Questions
what discoveries did you have in relation to your course?
Advantage of Aluminum form work in terms of activities can be skip and cost too
how to control PQI (Project Quality Index)
for G+2 residential building how much quantity of required in foundations,sub & superstructures per sq ft area
can i get hindi version of is codes based on civil engineering?
in levelling operation the first site on any change point is back site the second site on any change point is fore site the line commenses with fore sight & closes with backsight the line comensses with back sight & closes with fore sigh
How to Calculate Materials Required for PCC 1:4:8 for 1Cum & Brickwork 1:4 for 1Cum & Plastering 1:4 (15mm Thick) for 100Sqm & RCC 1:4:8 & 2mt ( L1=1mt & L2=1mt ) length of 12mm Steel bended in 90degrees what is the formula to calculate Weight & Actual Length ?
How to determine thee cut length for steel reinforcement bars in R.C.C design
what is your role of in previous company as a construction manager
how much cement and sand required for 100sqm of wall plastering in different proportions
If we have the center line of the Finnish road level and we want to know what level of pay would have offset the Lhs and Rhus RHS 1,2.5,5 1,2.5,5 m.
I just got a first job in Maharashtra and m a fresher. My task is estimate the cost of excavation of earth with J.C.B. can anyone tell me how to do this??
in 100 cft = 1350 bricks in 100 cft = ? bloks
How to come 1.54 from dry to wet concrete?
can stub column take the load as main column