What are the skills required to be a project manager?
Followup question, Rate yourself in each of the skill with
examples.
Answer Posted / meghanadh
1.Planning Skill
2.Contolling Skill
3.Organising Skill
4.Motivating and Leading Skill
5.Decision Making Skill
6.Communication Skill
they are the critical skills to be in a project manager.
| Is This Answer Correct ? | 14 Yes | 0 No |
Post New Answer View All Answers
You are the project manager for an upcoming outdoor concert event. You're working on the procurement plan for the computer software program that will control the lighting and screen projections during the concert. You're comparing the cost of purchasing a software product to the cost of your company programmers writing a custom software program. You are engaged in which of the following? A. Procurement planning B. Sensitivity analysis C. Transference of risk D. Make or buy analysis
What limits the options of the project team? A. Technology B. Constraints C. Deliverables D. Assumptions
Explain the Principals of Management
The tools and techniques of the Source Selection process include all of the following except: A. Contract negotiation B. Correspondence C. Independent estimates D. Screening system
What is the purpose of the project charter? A. To recognize and acknowledge the project sponsor B. To recognize and acknowledge the existence of the project and commit organizational resources to the project C. To acknowledge the existence of the project team, project manager, and project sponsor D. To describe the selection methods used to choose this project over its competitors
Which of the following is true regarding the critical path? A. It should never be compressed. B. It allows for looping and branching. C. The critical path technique is the same as PERT. D. It's the duration of all tasks with zero float.
You are a project manager for Dakota Software Consulting Services. You're working with a major retailer that offers their products through mail-order catalogs. They're interested in knowing customer characteristics, the amounts of first-time orders, and similar information. As a potential bidder for this project, you worked on the RFP response and submitted the proposal. When the selection committee received the RFP responses from all the vendors bidding on this project, they used a weighted system to make a selection. Which process did this occur in? A. Source Selection B. Solicitation C. Requisition D. Contract Administration
What is one of the problems with project management software? A. The project manager manages the software instead of the project B. Project duration calculations are sometimes approximate. C. You cannot override the project management software decisions regarding schedules. D. It’s expensive and difficult to use.
You work for a large manufacturing plant. You're working on a new project for an overseas product release. This is the company's first experience in the overseas market, and they hope to make a big splash with the introduction of this product. The project entails producing your product in a concentrated formula and packaging it in smaller containers than the U.S. product uses. A new machine is needed in order to mix the first set of ingredients in the concentrated formula. Which of the following is true? A. The new machine, the concentrated formula, and the smaller package are each project constraints. B. The new machine, the concentrated formula, and the smaller package description must be incorporated into the product description document. C. The new machine, the concentrated formula, and the smaller package are each project assumptions. D. The new machine, the concentrated formula, and the smaller package are each considered deliverables.
You are the project manager for the Late Night Smooth Jazz Club chain, with stores in 12 states. Smooth Jazz is considering opening a new club in Arizona or Nevada. You have derived the following information: Project Arizona: Payback period is 18 months, and the NPV is 250. Project Nevada: Payback period is 24 months, and the NPV is 300. Which project would you recommend to the selection committee? A. Project Arizona because the payback period is shorter than Project Nevada B. Project Nevada because the NPV is a positive number C. Project Arizona because the NPV is a negative number D. Project Nevada because the NPV is a higher number than Project Arizona's NPV
You are a project manager for an engineering company. Your company won the bid to add ramp-metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor's work involves digging the holes and setting the lamp poles in concrete. The subcontractor's performance is not meeting the contract requirements, because the poles are not buried to the correct depth. Which of the following is true? A. You are in the Quality Assurance process and have performed a quality audit to assure correctness of work. B. You are in the Scope Verification process and have performed a quality audit to assure correctness of work. C. You are in the Contract Administration process and have completed a contract audit to assure the subcontractor's performance meets the contract requirements. D. You are in the Performance Reporting process and have completed a performance review of the contractor's work.
You are a project manager working on contract. You’ve performed earned value analysis and discovered that the project will be completed on time and under the original estimated amount. This means the profit to your company will decrease as will your personal bonus. Which of the following should you do? A. Add activities to the project to increase the cost enough to meet the original estimated amount. B. Tell the customer you're adding additional requirements to the project chat were originally cut because of cost constraints. C. Inform the customer that the project is completed and has come in under budget. D. Bill the customer for the full amount of the contract as this was the original agreed-upon price.
Project managers have the highest level of authority and the most power in which type of organizational structure? A. Projectized B. Strong matrix C. Functional D. Balanced matrix
What is the process in the Executing process group that determines if the project satisfies quality standards, identifies lessons learned, and review quality management activities to verify the correct quality elements are being examined? A. Quality Control B. Quality Monitoring and Control C. Quality Assurance D. Scope Verification
You work for a company that writes hilling software programs for the communication industry. You've just been assigned a new project. The customer is located in a distant country that limits the number of foreigners allowed into the country. You identify this risk in your risk management plan. The critical point during the project is installation and setup. You might do which of the following given these circumstances? A. Use a design of experiments technique to develop a contingency plan. B. Develop a cause-and-effect diagram that identifies the contract type you should use for a project like this. C. Use sensitivity analysis to assist you in developing the appropriate risk response for this situation. D. Develop a contingency plan for installation.