I. Requirements are formally reviewed.
II. Requirements are formally approved.
III. Requirements are placed under configuration control.
IV. Requirements are implemented in code.

Using the above statements, when are requirements
considered baselined?

1. I and II
2. I, II, and III
3. I, II, III, and IV
4. I only
5. I, III, and IV


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Testing AllOther Interview Questions

What is the minimum criteria for white box?

1 Answers  


What is virtual address?

0 Answers  


When passing data values between different machines whith different operating system what problem have to be solved ?

1 Answers   Jomo Kenyatta University, MMUST Masinde Muliro University of Science and Technology, SAB, University,


How can you eliminate the product risk in your project?

0 Answers  


What is difference between JBOD and RAID?

0 Answers   IBM,






How much testing is enough?

0 Answers  


when we need testing

3 Answers  


Can somebody provide me some interview questions on Selenium? plz email on er.pallavikapoor@gmail.com

1 Answers  


What is mean by release notes?

1 Answers   TCS,


Draw the Framework Architecture of Selenium RC with combination of Selenium webdriver?

0 Answers   HCL,


plz give me any body some 3top UAT test cases, Advance thanks?

0 Answers  


Hi, I attended an interview recently. I was asked the following question Assuming that I am Test Manager. There are 20 resources out of which 12 are manual testers, 5 automation testers and 3 performance testers. There are a bunch of projects to be tested in the organisation, the projects belong to various technologies, say 20% of projects in Java, 20% of projects in SAP, 30% of projects in .NET, 30% of projects in C# What is your approach as Test Manager in testing? Pls let me know your approach on this.

6 Answers   CTS,


Categories