This measurement is the value of the work that's been completed to date:
A. PV
B. AC
C. EV
D. EAC
No Answer is Posted For this Question
Be the First to Post Answer
You are a project manager working for Mail House King. Your company processes orders for several mail-order catalog companies. Your project is to install new mail-sorting equipment and software. You’ve had some problems and experienced some variances so far during the project. Your project sponsor has asked for an EAC. You know the following information: PV = 800, BAC = 700, EV = 675, AC = 750, and ETC = 30. Which of the following is the correct EAC given the circumstances? A. 778 B. 780 C. 861 D. 833
What change would you like to bring in the management of your previous organization ?
How does a project manager can avoid the above given ten points for the success of project.
You are a project manager for Dakota Software Consulting Services. You're working with a major retailer that offers their products through mail-order catalogs. They're interested in knowing customer characteristics, the amounts of first-time orders, and similar information. As a potential bidder for this project, you worked on the RFP response and submitted the proposal. When the selection committee received the RFP responses from all the vendors bidding on this project, they used a weighted system to make a selection. Which process did this occur in? A. Source Selection B. Solicitation C. Requisition D. Contract Administration
Project selection criteria might include: A. Benefit measurement methods B. Constrained optimization analysis C. NPV calculations D. Potential market share or increased public perception
How to track your team members?
Which of the following is true? A. Discounted cash flow analysis is the least precise of the cash flow techniques as it does not consider the time value of money. B. NPV is the least precise of the cash flow analysis techniques as it assumes reinvestment at the discount rate. C. Payback period is the least precise of the cash flow analysis techniques as it does not consider the time value of money. D. IRR is the least precise of the cash flow analysis techniques because it assumes reinvestment at the cost of capital.
You are a project manager for an agricultural supply company. You have just completed and obtained sign-off on the scope statement for your new Natural Bug Busters project. A key stakeholder has informed you that a deliverable is missing from the scope statement. This deliverable is a critical success factor. You should do which of the following? A. Inform the stakeholder that work not stated in the scope statement is excluded from the project. B. Modify the scope statement to reflect the new deliverable. C. Inform the stakeholder that this deliverable can be included in the next project since sign-off has already been obtained. D. Modify the scope statement after an approved change request has been received from the stakeholder.
As a PMP, you will be required to comply with the Project Management Professional Code of Professional Conduct. This code refers to all of the following except: A. Reporting conflicts of interest B. Reporting experience and PMP status truthfully C. Complying with stakeholder requirements D. Complying with rules and policies of foreign countries
You are a project manager for an engineering company. Your company won the bid to add ramp-metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor's work involves digging the holes and setting the lamp poles in concrete. The subcontractor's performance is not meeting the contract requirements, because the poles are not buried to the correct depth. Which of the following is true? A. You are in the Quality Assurance process and have performed a quality audit to assure correctness of work. B. You are in the Scope Verification process and have performed a quality audit to assure correctness of work. C. You are in the Contract Administration process and have completed a contract audit to assure the subcontractor's performance meets the contract requirements. D. You are in the Performance Reporting process and have completed a performance review of the contractor's work.
You are working on a project that is similar in scope to a project performed last year by your company. You might consider which of the following? A. Using the previous project's alternatives identification as a template B. Reusing the previous project's benefit/cost analysis as justification for this project C. Using the previous project's WBS as a template D. Reusing the previous project's product description when writing the scope statement
Why would someone want to move from Operations to Project managemnet
2 Answers Extreme Networks, IBM,