You have been hired as a contract project manager for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for their customers. Customers must pre-register before being allowed to order wine over the Internet so that legal age can be established. You tested using data from Grapevine's existing database. This new module cannot be tested until the data from the existing system is loaded. This is an example of which of the following?
A. Preferential logic
B. Soft logic
C. Discretionary dependency
D. Hard logic


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

Which of the following describes the cost of quality associated with scrapping, rework, and downtime? A. Internal failure costs B. External failure costs C. Prevention costs D. Appraisal costs

0 Answers  


You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the company. Your lead engineer has given you the following estimates for a critical path activity: 60 days most likely, 72 days pessimistic, 48 days optimistic. What is the expected value, or weighted average? A. 54 B. 66 C. 60 D. 30

0 Answers  


You are project manager for an engineering company. Your company won the bid to add ramp-metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor's work involves digging the holes and setting the lamp poles in concrete. The subcontractor's performance is not meeting the contract requirements. All of the following are valid options except: A. You document the poor performance in written form and send the correspondence to the subcontractor change request through Contract Administration. B. You terminate the contract for poor performance and submit a change request through Contract Administration. C. You submit a change request through Contract Administration to ask the subcontractor to comply with the terms of the contract. D. You agree to meet with the subcontractor to see if a satisfactory solution can be reached.

0 Answers  


You are a project manager working on a new software product. Your company plans to market to businesses. The project sponsor told you that the project must be completed by September 1. The company plans to demo the new software product at a trade show in late September and therefore needs the project completed in time for the trade show. However, the sponsor has also told you that the budget is fixed at $85,000 and cannot be increased by even $10 due to overall budget cuts this year. You must complete the project within the given time frame and budget. Which of the following is the primary constraint for this project? A. Budget B. Quality C. Time D. Schedule

0 Answers  


The VP of customer service has expressed concern over a project you're involved in. His specific concern is that if the project is implemented as planned, he’ll have to purchase additional equipment to staff his customer service center. The cost is substantial and was not taken into consideration in the project budget. The project sponsor insists that the project must go forward as originally planned or the customer will suffer. Which of the following is true? A. The VP of customer service is correct. Since the cost was not taken into account at the beginning of the project, the project should not go forward as planned. Project initiation should he revisited to examine the project plan and determine how changes can be made to accommodate customer service. B. The conflict should be resolved in favor of the customer. C. The conflict should be resolved in favor of the project sponsor. D. The conflict should be resolved in favor of the VP of customer service.

0 Answers  






All of the following are types of project closures or endings except: A. Addition B. Integration C. Verification D. Extinction

0 Answers  


You are a project manager for a growing dairy farm. They offer their organic dairy products regionally and are expanding their operations to the West Coast. They're in the process of purchasing and leasing dairy farms to get operations under way. You are in charge of the network operations part of this project. An important deadline is approaching that depends on the successful completion of the testing phase. You've detected some problems with your hardware in the testing phase and discover that the hardware is not compatible with other network equipment. You take corrective action and exchange the hardware for more compatible equipment. Which of the following is true? A. This is not a corrective action involves human resources, not project resources. B. Corrective action is taken here to make sure the future project outcomes are aligned with the project plan. C. Corrective action is not necessary in this case as the future project outcomes aren't affected. D. Corrective action serves as the change request to authorize exchanging the equipment.

0 Answers  


You are a project manager for Laredo Pioneer’s Traveling Rodeo Show. You’re heading up a project to promote a new line of souvenirs to be sold at the shows. You need to gather the inputs to write the scope statement. You gather which of the following? A. Project charter, product description, assumptions, and constraints B. Project charter, product analysis, and cost benefit analysis C. Product description, product analysis, and project charter D. Product description, assumptions, constraints, and product analysis

0 Answers  


Each of the following describes an element of the Scope Definition process except: A. Breaking down the major deliverables of the project into smaller, manageable components B. Supporting detail C. Decomposition D. Improving the accuracy of time and cost estimates

0 Answers  


All of the following are true regarding the Executing processes except: A. Executing has one core process. B. The majority of the project budget is spent here. C. The greatest conflicts are schedule conflicts. D. Project performance is measured to identify variances.

0 Answers  


You are a project manager for a growing dairy farm. They offer their organic dairy products regionally and are expanding their operations to the West Coast. They're in the process of purchasing and leasing dairy farms to get operations under way. The sub project manager in charge of network operations has reported some hardware problems to you. You’re also having some other coordinating and integrating other elements of the project. Which of the following is true? A. You are in the Project Plan Execution process. B. Your project team doesn't appear to have the right skills and knowledge needed to perform this project. C. You are in the Information Distribution process. D. Your project team could benefit from some team-building exercises.

0 Answers  


You are a project manager for a manufacturing firm that produces Civil War-era replicas and memorabilia. You discover a design error during a test production run on your latest project. Which of the following is the most likely response to this problem? A. Reduce the technical requirements so that the error is no longer valid. B. Go forward with production and ignore the error. C. Go forward with production but inform the customer of the problem. D. Develop alternative solutions to address the error.

0 Answers  


Categories