Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


When a project is being performed under contract, the product description is provided by which of the following?
A. The buyer
B. The project sponsor
C. The project manager
D. The contractor


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

What is one of the advantages of a functional structure? A. All employees report to one manager and have a clear chain of command. B. All employees report to two or more managers, but project team members show loyalty to functional managers. C. The organization is focused on projects and project work. D. Teams are collocated.

0 Answers  


What is raid in project management?

0 Answers  


If you know expected value is 500 and the standard deviation is 12, you can say with approximately a 95 percent confidence rating which of the following? A. The activity will take between 488 and 512 days. B. The activity will take between 464 and 536 days. C. The activity will take between 494 and 506 days. D. The activity will take between 476 and 524 days.

0 Answers  


You are a project manager responsible for the construction of a new office complex. You are taking over for a project manager who recently left the company. The prior project manager completed the scope statement and scope management plan for this project. In your interviews with some key stakeholders, you conclude which of the following? A. They understand that the scope statement assesses the Stability of the project scope and outlines how to incorporate scope changes into the project. B. They understand that the scope management plan assesses the stability of the project scope and outlines how to incorporate scope changes into the project. C. They understand that the scope management plan is deliverables oriented and cost estimates can be easily derived it. D. They understand that the scope statement is deliverables oriented and cost estimates can be easily derived from it.

0 Answers  


You are a project manager for Picture Shades, Inc. They manufacture window shades for hotel chains that have replicas of Renaissance-era paintings on the inside of the shades. Picture Shades is taking their product to the home market, and you're managing the new project. They will offer their products at retail stores as well as on their website. You're developing the project schedule for this undertaking and have determined the critical path. Which of the following is true? A. You calculated the most likely start date and most likely finish dates, float time, and weighted average estimates. B. You calculated the activity dependency, and the optimistic and pessimistic activity duration estimates. C. You calculated the early and late start dates, early and late finish dates, and float times for all activities. D. You calculated the optimistic, pessimistic, and most likely duration times and the float times for all activities.

0 Answers  


What is eXtreme methodolgy ?

4 Answers  


You are the project manager for a new website for the local zoo. You need to perform Qualitative Risk Analysis. When you've completed this process, you'll produce all of the following outputs except: A. Overall risk ranking for the project B. List of prioritized risks C. Inputs to other processes D. List of risks for additional analysis and management

0 Answers  


You are implementing a sap project. implementation compled and development started and at that time you found that there is major problem with the system .It would take again time and customer is not happy with that ,in that case how do you convince customer?

2 Answers   Siemens,


You are a project manager for a telecommunications firm. You're working on a project that entails upgrading technical hardware and equipment. The estimated cost of the hardware and equipment is $1,725,000. You are reviewing products from three different vendors. One of the vendors offers you and your family the use of the company yacht for the upcoming three-day weekend. What is the most appropriate response? A. Thank them and accept. You don't believe there is a conflict of interest or an integrity issue at stake. B. Thank them and decline. You know this could be considered personal gain, which could call your integrity into question. C. Thank them and accept. Immediately report your actions to the project sponsor so that your motives are not called into question after the fact. D. Thank them and decline. You know this could be considered an integrity issue on the part of the vendor.

0 Answers  


Explain the concept of total quality management.

0 Answers   EX,


Which of the following compression techniques increases risk? A. Crashing B. Resource leveling C. Fast tracking D. Lead and lag

0 Answers  


You are a project manager for the information technology division of a local satellite TV broadcasting company. This spring, the chief information officer for your company gave you the project to convert and upgrade all the PCs in the department to the latest release of a specific desktop application. Prior to this conversion, all manner of desktop software existed on machines throughout the company and had caused increasing problems with sharing files and information across the company. A lot of unproductive hours were spent typing information into several formats. This project came about as a result of which of the following? A. Technological advance B. Business need C. Customer request D. Legal requirement

0 Answers  


Categories