The VP of customer service has expressed concern over a project you're involved in. His specific concern is that if the project is implemented as planned, he’ll have to purchase additional equipment to staff his customer service center. The cost is substantial and was not taken into consideration in the project budget. The project sponsor insists that the project must go forward as originally planned or the customer will suffer. Which of the following is true?
A. The VP of customer service is correct. Since the cost was not taken into account at the beginning of the project, the project should not go forward as planned. Project initiation should he revisited to examine the project plan and determine how changes can be made to accommodate customer service.
B. The conflict should be resolved in favor of the customer.
C. The conflict should be resolved in favor of the project sponsor.
D. The conflict should be resolved in favor of the VP of customer service.


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

What is raid in project management?

0 Answers  


product development vs IT services

6 Answers   Mphasis, Proteans,


Which of the following is true regarding the staffing management plan needed for project activities? It is an output of the Resource Planning process. A. It details the resource requirements and the quantity of resources needed for project activities. It is an output of the Resource Planning process. B. It details how and when staff resources will be brought on and take off the project. It is an output of the Organizational Planning process. C. It details how and when staff resources wilt be brought on and take off the project. It is an output of the Resource Planning process. D. It details the resource requirements and the quantity of resources needed for project activities. It is an output of the Organizational Planning process.

0 Answers  


You are the project manager for a top-secret software project for an agency of the United States Government. Your mission, should you choose to accept it, is to complete the project using internal resources. The reason is because getting top secret clearances for contractors takes quite a bit of time and waiting for clearances would jeopardize the implementation date. Your programmers are 80 percent of the way through the programming and testing work when your agency appoints a new executive director. Your programmer’s are siphoned off this project to work on the executive director's hot new project. Which of the following addresses the purpose of Scope Verification in this case? A. It determines the correctness and completion of all the work B. It documents the level and degree of completion C. It determines if the project results comply with quality standards D. It documents the correctness of the work according to stakeholders' expectations

0 Answers  


Which of the following is true? A. Discounted cash flow analysis is the least precise of the cash flow techniques as it does not consider the time value of money. B. NPV is the least precise of the cash flow analysis techniques as it assumes reinvestment at the discount rate. C. Payback period is the least precise of the cash flow analysis techniques as it does not consider the time value of money. D. IRR is the least precise of the cash flow analysis techniques because it assumes reinvestment at the cost of capital.

0 Answers  






You are a project manager for an engineering company. Your company won the bid to add ramp-metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor's work involves digging the holes and setting the lamp poles in concrete. The subcontractor's performance is not meeting the contract requirements, because the poles are not buried to the correct depth. Which of the following is true? A. You are in the Quality Assurance process and have performed a quality audit to assure correctness of work. B. You are in the Scope Verification process and have performed a quality audit to assure correctness of work. C. You are in the Contract Administration process and have completed a contract audit to assure the subcontractor's performance meets the contract requirements. D. You are in the Performance Reporting process and have completed a performance review of the contractor's work.

0 Answers  


The outputs of the Administrative Closure process include all of the following except: A. Project archives B. Project closure C. Lessons learned D. Formal acceptance

0 Answers  


The project schedule is used to determine all of the following except: A. Cost estimates B. Activity start dates C. Float times D. Activity end dates

0 Answers  


You are a project manager for Fountain of Youth Spring Water bottlers. You are installing a new accounting system and have identified several problems and their causes. You decide to use which of the following to identify the variables that will have the greatest effect on project outcomes? A. Design of experiments B. Bench marking C. Benefit/cost analysis D. Flow charting

0 Answers  


Your organization regularly uses a tool and technique of the Contract Closeout process to identify lessons learned, including the successes and failures, which will benefit future activity on this project and on future projects. Which tool and technique arc they using? A. Product documentation inspection B. Contract process review C. Performance measurement review D. Procurement audit

0 Answers  


Obtaining formal project plan approval and sign-off is important for all of the following reasons except: A. Stakeholders are able to recommend a project Planning methodology to follow throughout the remaining process groups. B. Stakeholders are aware of the project details, which make them more likely to participate in future project decisions. C. Stakeholders will be more likely to cooperate. D. Stakeholders are aware of the specific details regarding project schedules, budgets, and risks.

0 Answers  


You are a project manager for Zippy Tees. Your selection committee has just chosen a project you recommended for implementation. Your project is to manufacture a line of miniature stuffed bears that will be attached to your company's trendy T-shirts. The bears will be wearing the same T-shirt design as the shirt they're attached to. Your project sponsor thinks you've really impressed the big boss and wants you to skip to the manufacturing process right away. What is your response? A. To agree with the project sponsor because they are your boss, and they have a lot of authority and power in the company. B. To require that a preliminary budget be established and a resource list be put together to alert other managers of the requirements of this project. This should be published and signed by the other managers who are impacted by this project. C. To require a project charter be published and signed off on by all stakeholders before proceeding. D. To require a project charter be written to include the resource needed, budget, and project manager's authority. The project manager is the only one who needs to see this document as other documents will be distributed later that contain the same detail as the charter.

1 Answers  


Categories