What is the difference between contingency and mitigation
plan?
Answer / ritesh singhal
What is Risk Mitigation?
Mitigation is the process of solving problems that were caused or reducing the effect of the risk once it arises. In other words, risk mitigation strives to minimize a risk that materializes. Risk mitigation can also be seen as a method used to control damage that has already being done, and to reduce the ‘blow’ or consequences that it may have on the organization.
What is Contingency ?
Contingency is a planning process in which the company will come up with a few backup plans in the event that the risk materializes. A contingency plan is also known as the action plan for the worst case scenario. Such plans are essential to an organization as it helps organization quickly adapt to changes while suffering less consequences.
Mitigation vs Contingency
• Risk management is essential for organizations to ensure the long term smooth running of the business. There are two parts to risk management; risk mitigation and contingency planning.
• Mitigation is the process of solving the problems that were caused or reducing the effect of the risk once it arises.
• Contingency is a planning process in which the company will come up with a few backup plans in the event that the risk materializes.
• Risk mitigation is aimed at reducing the consequences of the crisis, whereas contingency planning is used to determine how problems can be solved if a crisis occurs.
| Is This Answer Correct ? | 5 Yes | 1 No |
How do you manage team performance?
What are the functions of project management tool?
You have been assigned to a project in which the objectives are to direct customer calls to an Interactive Voice Response system before being connected to a live agent. You are in charge of the media communications for this project. You report lo the project manager in charge of this project and the VP of marketing, who share responsibility for this project. Which organizational structure do you work in? A. Functional organization B. Weak matrix organization C. Projectized organization D. Balanced matrix organization
You are a project manager for a new software development project. You have a few activities that require specialized testing. The testing might need to be repeated more than once. Which of the following do you choose? A. The Graphical Evaluation and Review Technique because it allows for conditional branching and looping for the testing activity B. The Critical Path Method because it allows for float time to be calculated for the testing activity C. The Program Evaluation and Review Technique because it allows for conditional branching and looping for the testing activity D. The Program Evaluation and Review Technique because it allows for a weighted average distribution, which will even out the time needed for the testing activity
All of the following are types of project closures or endings except: A. Addition B. Integration C. Verification D. Extinction
Information-gathering techniques used in the Risk Identification process include all of the following except: A. Brainstorming B. Delphi technique C. Interviewing D. Kaizen technique
You are a project manager for Dakota Software Consulting Services. You're working with a major retailer that offers their products through mail-order catalogs. They're interested in knowing customer characteristics, the amounts of first-time orders, and similar information. The stakeholders have accepted the project scope. Work has begun on the project, and you're confirming some of the initial work results with the stakeholders. You've asked for acceptance of the work results. Which process are you in? A. Quality Assurance B. Quality Control C. Scope Verification D. Performance Reporting
Which of the following is true regarding NPV? A. NPV assumes reinvestment at the cost of capital. B. NPV decisions should be made based on the highest value for all of the selections. C. NPV assumes reinvestment at the prevailing rate. D.NPV assumes reinvestment at the NPV rate.
You have been hired as a contract project manager for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for their customers. Customers must pre-register before being allowed to order wine over the Internet so that legal age can be established. You tested using data from Grapevine's existing database. This new module cannot be tested until the data from the existing system is loaded. This is an example of which of the following? A. Preferential logic B. Soft logic C. Discretionary dependency D. Hard logic
You've constructed the WBS for your recent project. Level two assignments have been made, and you've requested that the sub project manager’s report back to you in 3 weeks with each of their individual WBS constructed. All of the following are true except: A. The work package level facilitates resource assignments. B. The work package level is the lowest level in the WBS. C. The work package level defines the agreed-upon deliverables. D. The work package level facilitates cost and time estimates. ?
You have been assigned to a project in which the objectives are to expand three miles of the north-south highway through your city by two lanes in each direction. You are interested in implementing a new project process called design-build in order to speed up the project schedule. The idea is that the construction team will work on the first mile of the highway reconstruction. At the same lime, the design team is coming up with plans for the third mile of the reconstruction rather than completing all design before any construction begins. This is an example of: A. Managing the projects as a program B. Fast tracking C. Progressive elaboration D. Collocation
Which performance measurement is the cost of work budgeted for an activity within a certain time frame? A. AV B. PV C. EV D. EAC