What is the difference between contingency and mitigation
plan?
Answer Posted / ritesh singhal
What is Risk Mitigation?
Mitigation is the process of solving problems that were caused or reducing the effect of the risk once it arises. In other words, risk mitigation strives to minimize a risk that materializes. Risk mitigation can also be seen as a method used to control damage that has already being done, and to reduce the ‘blow’ or consequences that it may have on the organization.
What is Contingency ?
Contingency is a planning process in which the company will come up with a few backup plans in the event that the risk materializes. A contingency plan is also known as the action plan for the worst case scenario. Such plans are essential to an organization as it helps organization quickly adapt to changes while suffering less consequences.
Mitigation vs Contingency
• Risk management is essential for organizations to ensure the long term smooth running of the business. There are two parts to risk management; risk mitigation and contingency planning.
• Mitigation is the process of solving the problems that were caused or reducing the effect of the risk once it arises.
• Contingency is a planning process in which the company will come up with a few backup plans in the event that the risk materializes.
• Risk mitigation is aimed at reducing the consequences of the crisis, whereas contingency planning is used to determine how problems can be solved if a crisis occurs.
| Is This Answer Correct ? | 5 Yes | 1 No |
Post New Answer View All Answers
All of the following are tools and techniques of the Integrated Change Control process except: A. Configuration management B. Performance measurements C. Change requests D. Additional planning
Your company has asked you to be the project manager for the product introduction of their new DeskTop Rock media system. You recently published a document that establishes the scope baseline. Which of the following is true? A. This is the scope statement, which is an output of the Scope Planning process. B. This is the scope statement, which is an output of the Scope Definition process. C. This is the scope statement, which is a tool and technique of the Scope Definition process. D. This is the scope management plan, which is an output of the Scope Definition process.
You are the project manager for Insomniacs International. Since you don't sleep much, you get a lot of project work done. You're considering recommending a project that costs $575,000, and expected inflows are $25,000 per quarter for the first 2 years, and then $75,000 per quarter thereafter. What is the payback period? A. 40 months B. 38 months C. 39 months D. 41 months
You are a project manager for Dutch Harbor Consulting. Your latest project involved the upgrade of an organization's operating system on 236 servers. You performed this project under contract. You are in the Contract Closeout process and know that you should document: A. Lessons learned B. Performance measurements C. Formal acceptance D. Product verification
If you know expected value is 500 and the standard deviation is 12, you can say with approximately a 95 percent confidence rating which of the following? A. The activity will take between 488 and 512 days. B. The activity will take between 464 and 536 days. C. The activity will take between 494 and 506 days. D. The activity will take between 476 and 524 days.
You are a project manager for Bluebird Technologies. Bluebird writes custom billing applications for several industries. One of your users verbally requests changes to one of the screen displays. You explain to her that the change needs to go through the change control system. You explain that a change control system does all of the following, except: A. Document procedures for change requests B. Track the status of change requests C. Describe the management impacts of change D. Determine if changes are approved or denied
You have been asked to submit a proposal for a project that has been put out for bid. First, you attend the bidders conference to ask questions of the buyers and to hear the questions some of the other bidders will ask. Which of the following is true? A. Bidders conferences are a tool and technique of the Source Selection process. B. Bidders conferences are an output of the Source Selection process. C. Bidders conferences are an output of the Solicitation process. D. Bidders conferences are a tool and technique of the Solicitation process.
You are the project manager for a scheduled version release of your company’s software tracking product. You have linked the WBS and project scope definition and assigned roles and responsibilities. You might want to display the roles and responsibilities in which of the following? A. RDM B. PDM C. AOA D. RAM
What is the name of the unplanned response used to deal with negative risk events in the Risk Monitoring and Control process? A. Mitigation B. Contingency plans C. Workarounds D. Corrective action
Explain the difference between Project management and IT management.
Explain the meaning of management.
You are refining the product description for your company's new line of ski boots. Which of the following is true? A. You are in the Initiation process of your project and know that the product description will contain more detail in this stage and that a decreasing amount of detail will be added to it as the project progresses. B. You are in the Planning process of your project and know that the product description will contain less detail in this stage and greater detail as the project progresses. C. You are in the Initiation process of your project and know that the product description should contain the most detail possible at this stage, as this is critical information for the Planning process D. You are in the Initiation process of your project and know that the product description will contain less detail in this stage and greater detail as the project progresses.
Each of the following describes an element of the Scope Definition process except: A. Breaking down the major deliverables of the project into smaller, manageable components B. Supporting detail C. Decomposition D. Improving the accuracy of time and cost estimates
This measurement is the value of the work that's been completed to date: A. PV B. AC C. EV D. EAC
You are a project manager for an agricultural supply company. You have just completed and obtained sign-off on the scope statement for your new Natural Bug Busters project. A key stakeholder has informed you that a deliverable is missing from the scope statement. This deliverable is a critical success factor. You should do which of the following? A. Inform the stakeholder that work not stated in the scope statement is excluded from the project. B. Modify the scope statement to reflect the new deliverable. C. Inform the stakeholder that this deliverable can be included in the next project since sign-off has already been obtained. D. Modify the scope statement after an approved change request has been received from the stakeholder.