During an IT audit of a large bank, an IS auditor observes
that no formal risk assessment exercise has been carried out
for the various business applications to arrive at their
relative importance and recovery time requirements. The risk
that the bank is exposed to is that the:
A. business continuity plan may not have been calibrated to
the relative risk that disruption of each application poses
to the organization.
B. business continuity plan may not include all relevant
applications and therefore may lack completeness in terms of
its coverage.
C. business impact of a disaster may not have been
accurately understood by the management.
D. business continuity plan may lack an effective ownership
by the business owners of such applications.
Answer / guest
Answer: A
The first and key step in developing a business continuity
plan is a risk assessment exercise that analyzes the various
risks that an organization faces and the impact of
non-availability of individual applications. Section 4.9.1.2
of BS 7799 (Standard on Information Security Management )
states that ?a strategy plan, based on appropriate risk
assessment, shall be developed for overall approach to
business continuity.?
| Is This Answer Correct ? | 3 Yes | 0 No |
Which of the following is MOST likely to result from a business process reengineering (BPR) project? A. An increased number of people using technology B. Significant cost savings, through a reduction in the complexity of information technology C. A weaker organizational structures and less accountability D. Increased information protection (IP) risk will increase
Separation of duties between computer opeartors and other data processing personnel is intended to: A. Prevent unauthorized modifications to program or data. B. Reduce overall cost of operations C. Allow operators to concentrate on their assigned duties D. Restrict operator access to data
The purpose for requiring source code escrow in a contractual agreement is to: A. ensure the source code is available if the vendor ceases to exist. B. permit customization of the software to meet specified business requirements. C. review the source code for adequacy of controls. D. ensure the vendor has complied with legal requirements.
The BEST overall quantitative measure of the performance of biometric control devices is: A. false rejection rate. B. false acceptance rate. C. equal error rate. D. estimated error rate.
Which of the following is the MOST effective type of antivirus software? A. Scanners B. Active monitors C. Integrity checkers D. Vaccines
Which of the following can consume valuable network bandwidth? A. Trojan horses B. Trap doors C. Worms D. Vaccines
An IS auditor reviewing an organization's IT strategic plan should FIRST review: A. the existing IT environment. B. the business plan. C. the present IT budget. D. current technology trends.
Which of the following would be a MAJOR disadvantage of using prototyping as a systems development methodology? A. User expectations of project timescales may be overly optimistic. B. Effective change control and management is impossible to implement. C. User participation in day-to-day project management may be too extensive. D. Users usually are not sufficiently knowledgeable to assist in system development.
Which of the following is an example of a passive attack, initiated through the Internet? A. Traffic analysis B. Masquerading C. Denial of service D. E-mail spoofing
Which of the following situations would increase the likelihood of fraud? A. Application programmers are implementing changes to production programs. B. Application programmers are implementing changes to test programs. C. Operations support staff are implementing changes to batch schedules. D. Database administrators are implementing changes to data structures.
Disaster recovery planning addresses the: A. technological aspect of business continuity planning. B. operational piece of business continuity planning. C. functional aspect of business continuity planning. D. overall coordination of business continuity planning.
During a post-implementation review of an enterprise resource management system, an IS auditor would MOST likely: A. review access control configuration. B. evaluate interface testing. C. review detailed design documentation. D. evaluate system testing.