All of the following are tools and techniques of the Schedule Development process except? A. CPM B. RAM C. GERT D. PERT

545

You are a project manager for a new software development project. You have a few activities that require specialized testing. The testing might need to be repeated more than once. Which of the following do you choose? A. The Graphical Evaluation and Review Technique because it allows for conditional branching and looping for the testing activity B. The Critical Path Method because it allows for float time to be calculated for the testing activity C. The Program Evaluation and Review Technique because it allows for conditional branching and looping for the testing activity D. The Program Evaluation and Review Technique because it allows for a weighted average distribution, which will even out the time needed for the testing activity

476

You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the company. Your lead engineer has given you the following estimates for a critical path activity: 60 days most likely, 72 days pessimistic, 48 days optimistic. What is the expected value, or weighted average? A. 54 B. 66 C. 60 D. 30

718

You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the company. Your lead engineer has given you the following estimates for a critical path activity: 60 days most likely, 72 days pessimistic, 48 days optimistic. What is the standard deviation? A. 22 B. 20 C. 2 D. 4

814

If you know expected value is 500 and the standard deviation is 12, you can say with approximately a 95 percent confidence rating which of the following? A. The activity will take between 488 and 512 days. B. The activity will take between 464 and 536 days. C. The activity will take between 494 and 506 days. D. The activity will take between 476 and 524 days.

525

If your expected value is ll0 and the standard deviation is l2, which of the following is true? A. There is approximately a 99 percent chance of completing this activity between 86 and 134 days. B. There is approximately a 68 percent chance of completing this activity between 98 and 122 days. C. There is approximately a 95 percent chance of completing this activity between 98 and 122 days. D. There is approximately a 75 percent chance of completing this activity between 86 and 134 days.

555

You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. The manager of the R&D department has agreed to release two resources to work on your project in order to meet the federal grant application date. This is an example of: A. Crashing B. Fast trucking C. Resource leveling D. Adjusting the resource calendar

664

You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. You adjust the schedule and find that two activities previously scheduled to start sequentially can be started at the same time. This is an example of: A. Crashing B. Fast tracking C. Resource leveling D. Adjusting the resource calendar

785

You are the project manager for Rivera Gourmet Adventure Vacations. Rivera combines the wonderful tastes of great gourmet food with outdoor adventure activities. Your project involves installing a new human resources software system. Jason, the database analyst working on this project, is over allocated. Which of the following is true? A. You should use resource requirements updates to determine availability and smooth out resource over allocation. B. You should use crashing to resource level the critical path tasks. C. You should use resource leveling heuristics to smooth out resource assignments. D. You should use fast tracking to resource level the critical path tasks.

1 1970

What is one of the problems with project management software? A. The project manager manages the software instead of the project B. Project duration calculations are sometimes approximate. C. You cannot override the project management software decisions regarding schedules. D. It’s expensive and difficult to use.

620

Obtaining formal project plan approval and sign-off is important for all of the following reasons except: A. Stakeholders are able to recommend a project Planning methodology to follow throughout the remaining process groups. B. Stakeholders are aware of the project details, which make them more likely to participate in future project decisions. C. Stakeholders will be more likely to cooperate. D. Stakeholders are aware of the specific details regarding project schedules, budgets, and risks.

911

Which of the following are the tools and techniques of the Cost Budgeting process? A. Project management information system, analogous estimating, bottom-up estimating, mathematical analysis B. Analogous estimating, bottom-up estimating, mathematical analysis, computerized tools C. Project management software, analogous estimating, bottom-up estimating, parametric modeling D. Analogous estimating, bottom-up estimating, parametric modeling, computerized tools

523

You are the project manager for a custom home-building construction company. You are working on the model home project for the upcoming Show Homes Tour. The model home includes Internet connections in every room and talking appliances. You are working on the cost budget for this project. Which of the following is true? A. This process assigns cost estimates to project activities including risks and contingency plans. B. The cost baseline will be used to measure variances and future project performance. C. This process assigns cost estimates for expected future period operating costs. D. The cost baseline is the expected cost for the project.

788

Which of the following is displayed as an S-curve? A. Gantt B. Cost baseline C. Critical path D. PERT

718

All of the following are true regarding the project plan except: A. Some of its inputs are outputs from other Planning processes. B. It's used to guide the project executing and controlling processes and is the baseline used to measure project performance. C. It consists of one document that should be formally approved and signed by stakeholders. D. It contains things like the WBS, project schedule, and resource assignments.

741


Un-Answered Questions { Software Design }

What all the major containerization tools in devops ?

1


Where can I get excellent free Business Analyst training online?

2450


What is difference between polymorphism and normalization?

1480


You are a project manager for Dutch Harbor Consulting. Your latest project involved the upgrade of an organization’s operating system on 236 servers. You performed this project under contract. You are in the Closing process and know that product verification is for what purpose? A. To verify the goals of the project and assure the product of the project is complete B. To evaluate all the work of the project and compare results to project scope C. To verify all the work was completed correctly and satisfactorily D. To evaluate project goals and assure the product of the project meets the requirements

648


What are main benefits of using mvc?

1






Can you give us a brief defining the architecture?

526


All of the following strategies are tools and techniques of Risk Response Planning used to reduce or control risk except? A. Mitigation B. Simulation C. Avoidance D. Acceptance

554


What is composition? Explain the purpose of composition.

555


Why is it required to have an abstraction layer in uml?

466


Describe two-factor authentication?

5


Why we need "Areas" in MVC?

5


What is mvc (model view controller)?

1


What is dynamic or run time polymorphism?

563


Suppose we have file(ps), dont know how many records are there. Move half of the records to 2 files. How can we do?

588


Why do we need singleton pattern?

593