Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...



Software Design Interview Questions
Questions Answers Views Company eMail

What is the purpose of the project charter? A. To recognize and acknowledge the project sponsor B. To recognize and acknowledge the existence of the project and commit organizational resources to the project C. To acknowledge the existence of the project team, project manager, and project sponsor D. To describe the selection methods used to choose this project over its competitors

1078

Which performance measurement tells us what the projected total cost of the project will be at completion? A. ETC B. CPI C. SPI D. EAC

1018

People are motivated by the need for achievement, power, or affiliation according to which theory? A. Expectancy theory B. Achievement theory C. Contingency theory D. Theory X

955

You are a project manager working in a foreign country. You observe that some of your project team members are having a difficult time adjusting to the new culture. You provided them training on cultural differences and the customs of this country before arriving, but they still seem uncomfortable and disoriented. Which of the following is true? A. This is the result of working with teams of people from two different countries. B. This condition is known as culture shock. C. This is the result of jet lag and travel fatigue. D. This condition is known as global culturalism.

1120

You are the project manager for a construction company that is building a new city and county office building in your city. You recently looked over the construction site to determine if the work to date was conforming to the requirements and quality standards. Which tool and technique of Quality Control are you using? A. Performance measurements B. Inspection C. Sampling D. Prevention

935

Which of the following is true regarding Administrative Closure? A. It occurs at the end of a project phase and at the end of the project. B. It occurs at the end of the project phase only. C. It occurs at the end of the project only. D. It is performed prior to Contract Closeout.

960

You are the project manager for Heart of Texas casual clothing company. Your project involves installing a new human resources system. You've identified the risks associated with this project and are ready for the next step. What is the next step? A. You will evaluate the risks and assign probabilities and impacts using Qualitative and/or Quantitative Risk Analysis. B. You will use the Delphi technique to confirm the risks you've detailed and identify others you may have missed. C. You must evaluate the risks and assign probabilities and impacts using both Qualitative Risk Analysis, which comes first, then Quantitative Risk Analysis. D. You will define the steps to take to respond to the risks and detail them in the risk response plan.

1382

The project sponsor has approached you with a dilemma. The CEO announced at the annual stockholders meeting that the project you're managing will be completed by the end of this year. The problem is that this is six months prior to the scheduled completion date. It's too late to go back and correct her mistake, and stockholders are expecting implementation by the announced date. You must speed up the delivery date of this project. Your primary constraint before this occurred was the budget. What actions can you take to help speed up the project? A. Hire more resources to get the work completed faster. B. Ask for more money so that you can contract out one of the phases you had planned to do with in-house resources. C. Utilize negotiation and influencing skills to convince the project sponsor to speak with the CEO and make a correction to her announcement. D. Examine the project plan to see if there are any phases that can be fast tracked, and then revise the project plan to reflect the compression of the schedule.

1129

During your project meeting, a problem was discussed and a resolution to the problem was reached. During the meeting, the participants started wondering why they thought the problem was such a big issue. Sometime after the meeting, you received and e-mail from one of the meeting members saying they've changed their mind about the solution reached in the meeting and need to resurface the problem. The solution reached during the initial project meeting is an example of which of the following conflict resolution techniques? A. Confrontation B. Forcing C. Smoothing D. Storming

1040

You are the project manager for Heartthrobs by the Numbers Dating Services. You're working on an updated Internet site that will display pictures as well as short bios of prospective heartbreakers. You've just completed your project staff assignments and published the project team directory. Which process are you in? A. Resource Planning B. Organizational Planning C. Project Development Planning D. Staff Acquisition

1093

Which of the following describes the Executing process? A. Project plans are put into action. B. Project performance measurements are taken and analyzed. C. Project plans are developed. D. Project plans are published.

1002

Each of the following describes an element of the Scope Definition process except: A. Breaking down the major deliverables of the project into smaller, manageable components B. Supporting detail C. Decomposition D. Improving the accuracy of time and cost estimates

924

Which of the following are tools and techniques of the Initiation process? A. Project selection methods and expert judgment B. Project selection criteria and expert judgment C. Constraints and assumptions and expert judgment D. Expert judgment and project charter

944

Your project involves the research and development of a new food additive. You’re ready to release the product to your customer when you discover that a minor reaction might occur in people with certain conditions. The reactions to date have been very minor, and no known long-lasting side effects have been noted. As project manager you should: A. Do nothing because the reactions are so minor that very few people will be affected. B. Inform the customer that you've discovered this condition and tell them you'll research it further to determine the impacts. C. Inform your customer that there is no problem with the additive release the product to them. D. Tell the customer you'll correct the reaction problems in the next batch but you'll release the first batch of product to them now to begin using.

1128

According to the Guide to the PMBOK, the project manager is identified and assigned during which process? A. As an input to the Initiation process B. As an input to the Planning process C. As an output of the Initiation process D. As an output of the Scope Planning process

1340


Un-Answered Questions { Software Design }

Mention what does model-view-controller represent in an mvc application?

1


What are all the operators that cannot be overloaded?

969


What is dependency?

983


You are a project manager for Dakota Software Consulting Services. You're working with a major retailer that offers their products through mail-order catalogs. They're interested in knowing customer characteristics, the amounts of first-time orders, and similar information. As a potential bidder for this project, you worked on the RFP response and submitted the proposal. When the selection committee received the RFP responses from all the vendors bidding on this project, they used a weighted system to make a selection. Which process did this occur in? A. Source Selection B. Solicitation C. Requisition D. Contract Administration

1129


What is the goal of erp/sap?

859


You are a project manager for a documentary film company. In light of a recent national tragedy, the company president wants to get a new documentary on the rescue efforts of the heroic firefighters to air as soon as possible. She's looking to you to make this documentary the best that's ever been produced in the history of this company. She guarantees you free rein to use whatever resources you need to get this project done quickly. However, the best photographer in the company is currently working on another assignment. Which of the following is true? A. The primary constraint is time because the president wants the film done quickly. She told you to get it to air as soon as possible. B. Resources are the primary constraint. Even though the president has given you free rein on resource use, you assume she didn't mean those actively assigned to projects. C. The schedule is the primary constraint. Even though the president has given you free rein on resource use, you assume she didn’t mean those actively assigned to projects. The photographer won’t be finished for another three weeks on his current assignment, so schedule adjustments will have to be made. D. The primary constraint is quality because the president wants this to be the best film ever produced by this company. She's given you free rein to use whatever resources needed to get the job done.

1106


How do you set goals for your team?

914


What are the elements which are utilized in the state chart diagram?

859


What is razor syntax?

1


What is mvp design pattern?

1149


What is a subclass?

1043


How to identify the actors in a ucd?

1001


give difference between generic & iterative process model.

2139


Explain about aggregation?

994


What is a pattern?

948