Method of findingthe dry ingredient quantity of 1 m3
concrete.
Answer Posted / tarique08
suppose, concrete mix ratio = 1:1.5:3
then, sum = 1 1.5 3 = 5.5
as we know,dry material required for 1 cum. of concrete =
1.54 cum.
then we can find -:
(1) cement = 1*1.54/5.5 = .28 cum. or .28cum.* 28.8= 8.06
bags.
(2) sand = 1.5* 1.54/5.5 = .42 cum.
or .42cum.* 35.3 = 14.83 cubic feet.
(3) coarse aggregate = 3* 1.54/5.5 = .84 cum.
or .84 cum.* 35.3 = 29.65 cubic feet.
so, dry ingredient quantity required for 1 m3 of concrete-:
cement = 8.06 bags.
sand = 14.83 cft.
coarse aggregate = 29.65 cft.
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
what are the changes in concrete pour height as per IS 456, 2009?
Dear Sir, I work in hydro project. I want to hire Scorpio/ Bolero on monthly basis. But how can i justified its amount (Hourly basic). Please solve my problem
what is the cost difference of a same structure when it is constructed with brick masonary and when it is constructed with block masonary and concrete as a frame structure????????????????????????
For what purpose bedding is used under storm water drains, explain?
20 mpa what is the quantity of cement sand and aggregate in one cubic meter of pcc non rainforcement concreate kindly answer including formaula thanks
For The preparation of goverment examination Which book i will prefer and by which way i will do the preparation for exam.
column at edge of a framed structure is uniaxial or biaxial. and is an interior column is biaxial
kindly mail me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates plz send my email id- VMANDAL91@gmail.com
Explain the various stages of the project planning process in construction?
Does degree of bend of rebars has any effect on strength of the member? For example- if a beam is designed with 45 degree bent up bar with respect to architechtural needs and is not 45 in practical so will there be any reduction in the strength of member?
for 200 kg of cement how is the mix proportion in kg for m25 grade of concrete
how to calculate Rate of analysis for 100 m3 Any ratio of concrete ? including labour
How to calculate the cement and fine aggregate requirement for solid block masonry works in terms of Sqm. 1. 400x200x200mm 2. 400x200x100mm 3. 600x200x100mm 4. 600x200x200mm I need the answer for 1 Sqm of solid block works.
Design a cantilever type retaining wall to retain sand for 4m above the ground. The sand fall slopes at the rate of 1 vertical to 2 horizontal. The weight of sand is 18000 N/m3, the angle of repose being 30. The safe bearing capacity of the soil is 200 kn/m2 at 1/25m below the ground level. Use m 15 concrete mix.
how much one carpenter can doing shuttering of slab in one day