If process order is technically closed, by mistake
I want to process that order again can I do it?

Answer Posted / arun k

If order is in teco status , then this order is irrelevant to mrp , all purchase requisation and planned order is cancelled for that order and capacity also cancelled for that order, first you need to do the revoke teco and process it

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what are the problems you faced in MRP?

1433


Difference between standard cost and variable cost.

1853


Tell one biggest task for you

1321


What are traffic lights in mrp?

735


What are basic dates?

645






What are the three 'mrp procedures'?

659


What is a 'product hierarchy'?

620


Explain what is the use of sap material view and list out other parameters where sap material view is applicable?

606


Explain Planning file entry.

1032


what are Standard keys

1649


How the processing time is calculated in a wc when both labor, machine categories exist?

595


Explain Availability check.

930


Explain what is plm (product lifecycle management) in sap pp and what is the use?

657


In implementation stage tell some standard scenario before AS-Is & TO-BE

1389


What is planning file entry

1874