i want to change some data like price, data etc in created
purchase order. but system is not allowing the same. as a
support SAP MM functional consultant what you would do?

Answer Posted / sahasra

1. check whether po is open or closed.
2. check whether any release procedure is created for po, then release the po.
3. If GR is created against the po then it cannot be changed unless the GR is cancelled or changed

Is This Answer Correct ?    2 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is mrp (material requirement planning) and what is the transaction code to access mrp list?

613


Explain batch management process.

904


Explain the 'transaction keys' in mm?

710


What are some of the options available to transfer materials from one plant to another?

683


What is the function of obyc?

827






Can someone please share me the FSD for SAP MM related?? It would be great help and thanks in advance.

893


Explain credit memo

669


What is the difference between planned and unplanned services?

649


What is the use of purchase info record?

656


Explain the types of pipeline stocks in sap mm

652


Can we have release procedure without classification for a po?

708


Outline the functions supported by material master?

834


How do we create consignment stocks?

697


Where the schedule margin key is customized?

763


Explain control data for scheduling agreements.

1169