i want to change some data like price, data etc in created
purchase order. but system is not allowing the same. as a
support SAP MM functional consultant what you would do?
Answer Posted / wills
There are settings available in release indicator, saying
that, no changes can be applicable once released. If u do
want to do changes, you need to set the release indicator
settings as 'CHANGABLE AFTER RELEASE' option
| Is This Answer Correct ? | 9 Yes | 0 No |
Post New Answer View All Answers
You can Ask any Technical Question Related to SAP MM Module AT Functional consultant level,Testing or end user level
What mrp procedures in consumption based planning?
What are various stock types?
If the recruiter is expecting thorough Knowledge\exp on the following topics:- o Material master o Vendor master o Purchasing o Release strategy o Inventory management What type of questions can i expect ? Please mention some important questions
What is sap? How is it used in industries?
What is the difference between a purchase order and a purchase requisition?
How will you map subcontracting process for project stock?
What are the terms planned delivery and gr processing time?
If you want to make item ok check boix as default then what will you do?
List the steps involved in automatic account assignment configuration.
What is the procedure to make the period indicator in the mrp2 view as āpā?
Outline the functions supported by material master?
In bom I mentioned item category as l but when I create po for sub-contracting defaultly it shows t?
What are some of the other erp applications available in the market?
How do you generate an automatic po after creating a pr using a particular material?