IN THIRD PARTY SALES CUSTOMER PLACE ORDER 10PC, P.O CREATED
FOR 10PC BUT VENDOR ABLE DELIVER ONLY 8PC TO CUSTOMER THEN
WE WANT UPDATE SALES ORDER TO 8PC THEN HOW WE WILL DO IT.
Answer Posted / baskar
Dhanesh Tare answer is correct but I think we have to keep
the PO also manually changed. Once a PO is executed, the
changes made in Sales order does not reflect.
This will settle the further discrepancies that may arise
while doing a GR for the PO.
Is This Answer Correct ? | 5 Yes | 2 No |
Post New Answer View All Answers
I created a new info structure and activated update rules for it. What is the best way to transport them into a productive system?
How do you define document numnber ranges
Where do we can find pricing procedure indicator in sd ?
I was faced these interview questions, please provide answer with your real life experience SAP gurus. 1. As a SAP SD consultant how did you integrate/interact with MM and FI/CO? 2. Tell me about your OTC process expreience? 3. How have you used MASS tool in your last project, and to upgrade what data? 4. Tell me about your EDI/IDOC experience? PLease answer any/all questions as per your wish. Thank you very much in advance, god bless.
What are the effects of posting goods issue? Explain.
What is sap sales and distribution?
What is the path to define condition type in sap for pricing?
131. Are you familiar with billing output determination? Suppose if I’m creating an invoice, and I want to print out the output of the invoice, how would I do that? Are you familiar with any output that prints out SAP for that invoice so further delivery for example, in delivery you have backing slips delivery....
Hi SD Gurus, Have you involved in any Development work for your client? What is the development task that you done for your client / assigned by your client? I want only Business Scenarios, no theory and how did you meet the client requirement which is not met by SAP Standard configuration? I want detailed Procedure, Analysis, Simple coding if any (Please Do not give complex coding steps) Detailed explanation, steps, along with resolution and give more emphasis on how did you arrived at the solution / resolution and logic behind it? I have been asked this question in an recent interview? It’s Urgent!!!!!! Please provide 2-4 real time data examples from your SAP SD Implementation Project? This is most frequently asked question in almost in all interviews. So, I request you to provide solutions to above question as early as possible? Your timely help would be greatly appreciated? Thanks in advance Regards
what is settlement profile...when i m doing varient configuration i am facing this problem while creating sales order plz explain me......
What is the procedure to handle reservation process in sap SD?
Explain credit management.
What is item category and how is it determined?
To extend material one plants to another plant what are the configuration you done in your project?
What is the Difference between WM and EWM?