You are a project manager for Cinema Snicker Productions. Your company specializes in producing comedy films for the big screen. Your latest project has just been canceled due to budget cuts. Which of the following is true?
A. This project ended due to starvation because the funding was cut off
B. This project ended due to integration because the resources were distributed elsewhere
C. This project ended due to starvation because the resources were distributed elsewhere
D. This project ended due to integration because the funding was cut off


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

Describe the risk in software engineering.

0 Answers  


How do you set goals for your team?

0 Answers  


You are preparing a diagram that plots two variables, the dependent variable and the independent variable, to see the relationship between the two elements. What kind of diagram are you using? A. Cause-and-effect diagram B. Control chart C. Flowchart D. Scatter diagram

0 Answers  


What are the five project management process groups, in order? A. Initiation, Executing, Planning, Controlling, and Closing B. Initiation, Controlling, Planning, Executing, and Closing C. Initiation, Planning, Controlling, Executing, and Closing D. Initiation, Planning, Executing, Controlling, and Closing

0 Answers  


As a PMP, you will be required to comply with the Project Management Professional Code of Professional Conduct. This code refers to all of the following except: A. Reporting conflicts of interest B. Reporting experience and PMP status truthfully C. Complying with stakeholder requirements D. Complying with rules and policies of foreign countries

0 Answers  






You are a project manager responsible for the construction of a new office complex. You are taking over for a project manager who recently left the company. The prior project manager completed the scope statement and scope management plan for this project. In your interviews with some key stakeholders, you conclude which of the following? A. They understand that the scope statement assesses the Stability of the project scope and outlines how to incorporate scope changes into the project. B. They understand that the scope management plan assesses the stability of the project scope and outlines how to incorporate scope changes into the project. C. They understand that the scope management plan is deliverables oriented and cost estimates can be easily derived it. D. They understand that the scope statement is deliverables oriented and cost estimates can be easily derived from it.

0 Answers  


Which of the following describes the cost of quality associated with scrapping, rework, and downtime? A. Internal failure costs B. External failure costs C. Prevention costs D. Appraisal costs

0 Answers  


You are the project manager for a software consulting firm that is working on developing a new software program for a customer in another country. Things seem to be progressing well. Recently, your stakeholders examined the work of the project and formally accepted the work results. Which process was just performed? A. Scope Verification B. Quality Assurance C. Performance Reporting D. Quality Control

0 Answers  


what do u mean by an interview? no explanations but define.

18 Answers   CTS,


The Project Management Knowledge Areas: A. Include Initiation, Planning, Executing, Controlling, and Closing B. Consist of nine different areas that bring together processes that have things in common C. Consist of five different processes that bring together phases of projects that have things in common D. Include Planning, Executing, and Controlling processes as these three processes are commonly interlinked

0 Answers  


You are the project manager for BB Tops, a nationwide toy store chain. You are working on estimates for your latest project and have gathered several variables for your model. You've determined the following: A. Parametric modeling is a top-down technique that uses variables to produce time estimates. B. Parametric modeling is a mathematical formula that uses variables to produce cost estimates. C. Contingency estimating is a top-down technique that uses variables to produce cost estimates. D. Contingency estimating is a mathematical model that uses variables to produce time estimates.

0 Answers  


You are a project manager for Cinema Snicker Productions. Your company specializes in producing comedy films for the big screen. Your latest project has just been canceled due to budget cuts. Which of the following is true? A. This project ended due to starvation because the funding was cut off B. This project ended due to integration because the resources were distributed elsewhere C. This project ended due to starvation because the resources were distributed elsewhere D. This project ended due to integration because the funding was cut off