Many IT projects experience problems because the development
time and/or resource requirements are underestimated. Which
of the following techniques would provide the GREATEST
assistance in developing an estimate of project duration?

A. Function point analysis

B. PERT chart

C. Rapid application development

D. Object-oriented system development



Many IT projects experience problems because the development time and/or resource requirements are ..

Answer / guest

Answer: B

Function point analysis is a technique for determining the
size of a development task based on the number of function
points. Function points are factors such as inputs, outputs,
inquiries, logical internal file, etc. While this will help
determine the size of individual activities, it will not
assist in determining project duration since there are many
over-lapping tasks. A PERT chart will help determine project
duration once all the activities and the work involved in
the activities are known. Rapid application development is a
methodology that enables organizations to develop
strategically important systems faster while reducing
development costs and maintaining quality, and
object-oriented system development is the process of
solution specification and modeling.

Is This Answer Correct ?    5 Yes 0 No

Post New Answer

More CISA Certification Interview Questions

An IS auditor evaluates the test results of a modification to a system that deals with payment computation. The auditor finds that 50 percent of the calculations do not match predetermined totals. Which of the following would MOST likely be the next step in the audit? A. Design further tests of the calculations that are in error. B. Identify variables that may have caused the test results to be inaccurate. C. Examine some of the test cases to confirm the results. D. Document the results and prepare a report of findings, conclusions and recommendations.

1 Answers  


An organization is considering connecting a critical PC-based system to the Internet. Which of the following would provide the BEST protection against hacking? A. An application-level gateway B. A remote access server C. A proxy server D. Port scanning

2 Answers  


Which of the following is a threat? A. Lack of security B. Loss of goodwill C. Power outage D. Information services

1 Answers  


Which of the following findings would an IS auditor be MOST concerned about when performing an audit of backup and recovery and the offsite storage vault? A. There are three individuals with a key to enter the area. B. Paper documents also are stored in the offsite vault. C. Data files, which are stored in the vault, are synchronized. D. The offsite vault is located in a separate facility.

1 Answers   Apple,


A tax calculation program maintains several hundred tax rates. The BEST control to ensure that tax rates entered into the program are accurate is: A. an independent review of the transaction listing. B. a programmed edit check to prevent entry of invalid data. C. programmed reasonableness checks with 20 percent data entry range. D. a visual verification of data entered by the processing department.

1 Answers  






An integrated test facility is considered a useful audit tool because it: A. is a cost-efficient approach to auditing application controls. B. enables the financial and IS auditors to integrate their audit tests. C. compares processing output with independently calculated data. D. provides the IS auditor with a tool to analyze a large range of information.

2 Answers  


1. which of the following is used to achieve accountability. a.identification b. authentication c. authorization d. iniation

5 Answers  


The use of a GANTT chart can: A. aid in scheduling project tasks. B. determine project checkpoints. C. ensure documentation standards. D. direct the post-implementation review.

2 Answers  


The PKI element that manages the certificate life cycle, including certificate directory maintenance and certificate revocation list (CRL) maintenance and publication is the: A. certificate authority. B. digital certificate. C. certification practice statement. D. registration authority.

2 Answers  


Which of the following is an example of a passive attack, initiated through the Internet? A. Traffic analysis B. Masquerading C. Denial of service D. E-mail spoofing

2 Answers  


The potential for unauthorized system access by way of terminals or workstations within an organization's facility is increased when: A. connecting points are available in the facility to connect laptops to the network. B. users take precautions to keep their passwords confidential. C. terminals with password protection are located in unsecured locations. D. terminals are located within the facility in small clusters under the supervision of an administrator.

1 Answers  


IT governance ensures that an organization aligns its IT strategy with: A. Enterprise objectives. B. IT objectives. C. Audit objectives. D. Finance objectives.

2 Answers  


Categories
  • Cisco Certifications Interview Questions Cisco Certifications (2321)
  • Microsoft Certifications Interview Questions Microsoft Certifications (171)
  • Sun Certifications Interview Questions Sun Certifications (45)
  • CISA Certification Interview Questions CISA Certification (744)
  • Oracle Certifications Interview Questions Oracle Certifications (64)
  • ISTQB Certification Interview Questions ISTQB Certification (109)
  • Certifications AllOther Interview Questions Certifications AllOther (295)