Which of the following would BEST ensure continuity of a
wide area network (WAN) across the organization?

A. Built-in alternative routing

B. Full system backup taken daily

C. A repair contract with a service provider

D. A duplicate machine alongside each server



Which of the following would BEST ensure continuity of a wide area network (WAN) across the organiz..

Answer / guest

Answer: A

Alternative routing would ensure the network would continue
if a server is lost or if a link is severed as message
rerouting could be automatic. System backup will not afford
immediate protection. The repair contract is not as
effective as permanent alternative routing. Standby servers
will not provide continuity if a link is severed.

Is This Answer Correct ?    8 Yes 0 No

Post New Answer

More CISA Certification Interview Questions

An offsite information processing facility: A. should have the same amount of physical access restrictions as the primary processing site. B. should be easily identified from the outside so that in the event of an emergency it can be easily found. C. should be located in proximity to the originating site so that it can quickly be made operational. D. need not have the same level of environmental monitoring as the originating site since this would be cost prohibitive.

1 Answers  


Functionality is a characteristic associated with evaluating the quality of software products throughout their lifecycle, and is BEST described as the set of attributes that bear on the: A. existence of a set of functions and their specified properties. B. ability of the software to be transferred from one environment to another. C. capability of software to maintain its level of performance under stated conditions. D. relationship between the performance of the software and the amount of resources used.

1 Answers  


When performing a review of the structure of an electronic funds transfer (EFT) system, an IS auditor observes that the technological infrastructure is based on a centralized processing scheme that has been outsourced to a provider in another country. Based on this information, which of the following conclusions should be the main concern of the IS auditor? A. There could be a question with regards to the legal jurisdiction. B. Having a provider abroad will cause excesive costs in future audits. C. The auditing process will be difficult because of the distances. D. There could be different auditing norms.

2 Answers  


Applying a digital signature to data traveling in a network provides: A. confidentiality and integrity. B. security and nonrepudiation. C. integrity and nonrepudiation. D. confidentiality and nonrepudiation.

2 Answers  


The MOST appropriate person to chair the steering committee for a system development project with significant impact on a business area would be the: A. business analyst. B. chief information officer. C. project manager. D. executive level manager.

1 Answers  






An IS auditor when reviewing a network used for Internet communications, will FIRST examine the: A. validity of passwords change occurrences. B. architecture of the client-server application. C. network architecture and design. D. firewall protection and proxy servers.

1 Answers  


The purpose of debugging programs is to: A. generate random data that can be used to test programs before implementing them. B. protect, during the programming phase, valid changes from being overwritten by other changes. C. define the program development and maintenance costs to be include in the feasibility study. D. ensure that program abnormal terminations and program coding flaws are detected and corrected.

2 Answers   KPMG,


Disaster recovery planning addresses the: A. technological aspect of business continuity planning. B. operational piece of business continuity planning. C. functional aspect of business continuity planning. D. overall coordination of business continuity planning.

1 Answers  


An IS auditor is reviewing the change management process for an enterprise resource planning (ERP) application. Which of the following is the BEST method for testing program changes? A. Select a sample of change tickets and review them for authorization. B. Perform a walk-through by tracing a program change from start to finish. C. Trace a sample of modified programs to supporting change tickets. D. Use query software to analyze all change tickets for missing fields.

2 Answers  


If an application program is modified and proper system maintenance procedures are in place, which of the following should be tested? The: A. integrity of the database B. access controls for the applications programmer C. complete program, including any interface systems D. segment of the program containing the revised code

1 Answers  


Which of the following is a substantive test?

3 Answers  


An organization is considering connecting a critical PC-based system to the Internet. Which of the following would provide the BEST protection against hacking? A. An application-level gateway B. A remote access server C. A proxy server D. Port scanning

3 Answers  


Categories
  • Cisco Certifications Interview Questions Cisco Certifications (2321)
  • Microsoft Certifications Interview Questions Microsoft Certifications (171)
  • Sun Certifications Interview Questions Sun Certifications (45)
  • CISA Certification Interview Questions CISA Certification (744)
  • Oracle Certifications Interview Questions Oracle Certifications (64)
  • ISTQB Certification Interview Questions ISTQB Certification (109)
  • Certifications AllOther Interview Questions Certifications AllOther (295)