In a thermal power plant ID Fans running with full load but
boiler load is only 80 % give reason ?

Answer Posted / y v subba rao

If the moisture content in fuel is more than designed fuel, id fans has to run at full rpm to sent out the additional water vapor produced from the additional moisture. In fact total flue gas quantity was increased

Is This Answer Correct ?    3 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what is the trip circuit supervision in an electrical meaning?

1441


How do you consider that you can improve and what assistance do you need to achieve this

1332


By any way can we increase the B check hours from 300 to 500

1695


why airtel use + 24 volts and other operators use -48 volt

2106


LAPT working in alternator / generator

2545






DCS marshaling Cabinet Power supply can be replace during plant running time? Answer Yes it is possible. I am talking about the controller and cards power supply modules. They are always redundant and connected through diode so that if one power supply fails the other can take the charge immediately.so it is possible to replace one of them in running plant if the other one is healthy. MY question is how switching done.

514


Looking for Bently Nevada surplus 3300/52-01-00-00 Reverse Rotation Monitor , 4 pieces.

2979


what is restricted earth fault explain in details

1623


what does mean by kva rating

995


Which will have more strain energy 1.Spring 2.Circular disc 3.Solid square plate.

1880


what's the moog valve

1050


some one can tell me how residual type excitation is provided through transformers to an AC generator without any battery or PMG&excitor

1948


what is the difference between compensated & normal drum level in boiler drum?

1288


Qatar Fertiliser Company (QAFCO) Shortlisted me for interview (got the intel from my source) for Field Operator- Utilities post. Please let me know what kind of questions they asked? ... this position requires 5 years of experience in Power Plant and background Diploma in Electrical/ Mech. ... my Background is Electrical and I am a sub Assistant Engineer (Operation) at a private HFO based Power plant... PS: Please Let me know what preparation should I take to obtain the Interview which will be take place In Bangladesh soon

1765


what is the meaning of SST300 V56A in SIEMENS turbine

3885