In a thermal power plant ID Fans running with full load but
boiler load is only 80 % give reason ?
Answer Posted / y v subba rao
If the moisture content in fuel is more than designed fuel, id fans has to run at full rpm to sent out the additional water vapor produced from the additional moisture. In fact total flue gas quantity was increased
Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
what is the trip circuit supervision in an electrical meaning?
How do you consider that you can improve and what assistance do you need to achieve this
By any way can we increase the B check hours from 300 to 500
why airtel use + 24 volts and other operators use -48 volt
LAPT working in alternator / generator
DCS marshaling Cabinet Power supply can be replace during plant running time? Answer Yes it is possible. I am talking about the controller and cards power supply modules. They are always redundant and connected through diode so that if one power supply fails the other can take the charge immediately.so it is possible to replace one of them in running plant if the other one is healthy. MY question is how switching done.
Looking for Bently Nevada surplus 3300/52-01-00-00 Reverse Rotation Monitor , 4 pieces.
what is restricted earth fault explain in details
what does mean by kva rating
Which will have more strain energy 1.Spring 2.Circular disc 3.Solid square plate.
what's the moog valve
some one can tell me how residual type excitation is provided through transformers to an AC generator without any battery or PMG&excitor
what is the difference between compensated & normal drum level in boiler drum?
Qatar Fertiliser Company (QAFCO) Shortlisted me for interview (got the intel from my source) for Field Operator- Utilities post. Please let me know what kind of questions they asked? ... this position requires 5 years of experience in Power Plant and background Diploma in Electrical/ Mech. ... my Background is Electrical and I am a sub Assistant Engineer (Operation) at a private HFO based Power plant... PS: Please Let me know what preparation should I take to obtain the Interview which will be take place In Bangladesh soon
what is the meaning of SST300 V56A in SIEMENS turbine