Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

What do you mean by ASAP methodology? Explain in detail
about the different phases / Stages in ASAP methodology?
I have an interview in immediate future so plzz help
me...Please reply asap... Urgent!!!! Waiting for your
response eagerly... Thanks in advance

Answer Posted / katta gopichand

1) Project Preparation : where the SAP consultants try to understand the AS IS business process of the industry for which implementation is being done. The hardware and software requirements are analysed. Infact all the basic preparation is done at this stage.

2) Blue Print : After the AS IS study is made a TO BE process is evolved where in the client business is put in technically as to how it would be like in SAP. Blue is a binding between the implementor and Client. So, there is a sign off from the client on what is going to be done.

3) Realization : Here the blue print is configured on the system. For some processes where SAP cannot do as it is,like when there is a difference between AS IS and TO BE called a GAP , we use developers(ABAP) . The functional guys give the functional spec based on which the ABAP'rs prepare technical specs and fulfill the object ( may be reports, user exits, enhancements and so on). Also the unit and integration testing is done here.

4) Final Preparation : Here the enduser, core user training is completed on how he has to use the sap system. Master data uploads into the production server. In a way the system is getting for going live. And just before the go live date the data that needs to be put into sap is fixed and the remaining transactions of the business are recorded may be in a flat file or sometimes they are taken off so that upto date data in the production server is maintainted.

5) Go Live and Support : Here finally the SAP system goes live and followed by some support as agreed upon in the service level agreements .

Is This Answer Correct ?    4 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

In Order - what have you done exactly, did you do the entire setup in SAP, and if yes, can you walk me through it?

954


What is an mrp type?

1179


List the basic elements of a customer master record?

1125


Name the necessary steps to setup a route?

1149


Explain what is proforma invoice and what are the types of it?

1142


Is there an user exit to copy the data into planning table?

1159


Which partner function is relevant when it comes to tax calculation in the sales order?

1292


Tax jurisdiction processing is a close link between which two modules?

1201


What is the difference between pgi cancellation and returns order?

1248


What is a client?

1227


What is backorder processing or partial delivery?

1167


In case of third party sales what would trigger for the automatic creation of pr or po?

1247


what are all the shipment activities.explain this process pls. its very urgent and what is t-code.

2149


What are the important organizational elements of sap sd?

1109


What are the different contract types? How to create a contract in sap system?

1237