i want to make this calution for making a buliding but i
dont know the formula for this and also how much cement
concrete an sand use for this calculation,calculation is
below(100ft lenths 75ftwidth and 100mm thikness)plz brife
the calcution thanks
Answer Posted / jitender mishra
T0TAL QTY.100X75X.32=2400/35.31=67.96 M3
IF THE MIX-1:2:4
1/7=0.142X1.52=.217M3 CEMENT
.217/28.28=6.13BAG CEMENT
=.217*2=.434M3 SAND
=.217*4=.868M3 ARRREGATE
| Is This Answer Correct ? | 2 Yes | 6 No |
Post New Answer View All Answers
all technical question
How many mortar required for Brickwork of 1 Cu.m works??
How to test cement,sand,20mmbluemetal,40mmbluemetal,bricks,concrete by visual and instrument
How much cement and water required for cement selery????
What is need for setting limits?
what is the maximum number of course that can be laid according to IS code and the max height.
how can calculate cutting length of diamond ring
When was the first motorway built in england?
if i used salt as a add mixture in concrete, then what will happen and what are the naturally available add mixtures.
Describe the advantages and disadvantages of using plastic and timber fenders?
Required amount of Steel bars, cement/ square feet for roofing of residential building upto 3rd floor.
How to find permissible diagonal tensile stress in reinforced brick work
In a beam,stirrups are placed closely at ends than at centre due to shear.similarly where would ties be closer to each other-at center or at ends in a column and slab.
For what purpose bedding is used under storm water drains?
Can we use concrete of slump cone in cube casting in which we have already measured slump?