What is the power factor you maintain at ur organization?
Answer Posted / v.sureshkumar
i am maintain the power factor .85 to .9 in generation
plant.
power factor is ratio between the kva & kw ( active power &
reactive power) but basically in three typesof load is
there resistance load for lighting load that load is
maintain .95 to 1, inductive load based on induction
motor,incandesent lamp,welding transformer that load is
maintain .8 to .85 then over all power factor is
maintin .85 to .9 with additional load condition is
maintain apfc ( automatic power factor correction)capacitor
bank
| Is This Answer Correct ? | 2 Yes | 3 No |
Post New Answer View All Answers
Single line diagrams for star to delta and DOL starters.
What is tranformer differtial?
in a solar power plant,we are going to step up the voltage 350V to 33kv, and to 132kv GSS. i want to ask that if it is possible that 315v/33kv is not possible because we also use 315v/11kv. or it should be 415v/33kv? is it effects generation or losses? the second question is-generation is depends on LV winding? or LV winding design for generation voltage?
Why the field rheostat is adjusted such that the voltmeter reads 380V
how we start 40w tube light with 4 diodes,2capacitors,1 choke and without starter.(a product avilable in market which lights burnt tube lights also)
what do u understand about FACTS? how they are useful?
i have completed deee and i've (June2012-feb 2015 experience in electrical maintenance in pvt ltd company.company having HT & LT electrical power.how to apply electrical C-license ,NOW I was resigned my job,what are requirements of applying for c-license
direction of tarbine& genrator
how to select overload-relay for perticular motor 1.for D.O.L. starter 2. for Star-delta starter ????
i want to know that what is the eligibility critaria for ongc exam?
What is a compensator?
What are the necessary solutions needed to be carried out on a malfunctioned earthing mechanism of a VACUUM CIRCUIT BREAKER.(TAMCO)
How the setting of the vector surge relay shall be calculated when the relay is to be used for Grid islanding application?
mccb service sittings be done?
What is process of anneling transformer core