Suppose you did all your work in a 32 bit system, the
production server is 64 bit system, you find that during
UAT, the system fails and is not working, how will u
communicate to your customer, what solution will you
provide to the client?

Answer Posted / ck

First list out the possible reasons why it is failed and
also list out possible solutions...Then inform the customer
with effort required if possible with revised dates

Is This Answer Correct ?    0 Yes 7 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Your hardware vendor left you voicemail saying that a snowstorm in the Midwest will prevent your equipment from arriving on time. You identified a risk response for this risk and have arranged for a local company to lease you the needed equipment until yours arrives. This is an example of which risk response strategy? A. Transference B. Acceptance C. Mitigation D. Avoidance

770


Your selection committee meets on a semiannual basis. They've determined that projects must meet or exceed a specific profit limit in order to be accepted and prioritized on the project list. Which of the following is true? A. The selection committee has defined project selection criteria, which is a tool and technique of Initiation. B. The selection committee has defined project selection methods, which is a tool and technique of Initiation. C. The selection committee has defined project selection methods, which is an input to Initiation. D. The selection committee has defined project selection criteria, which is an input to Initiation.

613


Which organization has set the de facto standards for project management techniques? A. PMBOK B. PMO C. PMI D. PMA

1190


How do you set goals for your team?

476


Three people are responsible for establishing cost of quality theories. Crosby and Juran are two of them, and their theories respectively are: A. Grades of quality, fitness for use B. Fitness for use, zero defects C. Zero defects, fitness for use D. Cost of quality, zero defects

550






The project sponsor has approached you with a dilemma. The CEO announced at the annual stockholders meeting that the project you're managing will be completed by the end of this year. The problem is that this is six months prior to the scheduled completion date. It's too late to go back and correct her mistake, and stockholders are expecting implementation by the announced date. You must speed up the delivery date of this project. Your primary constraint before this occurred was the budget. What actions can you take to help speed up the project? A. Hire more resources to get the work completed faster. B. Ask for more money so that you can contract out one of the phases you had planned to do with in-house resources. C. Utilize negotiation and influencing skills to convince the project sponsor to speak with the CEO and make a correction to her announcement. D. Examine the project plan to see if there are any phases that can be fast tracked, and then revise the project plan to reflect the compression of the schedule.

693


You are a project manager for the information technology division of a local satellite TV broadcasting company. This spring, the chief information officer for your company gave you the project to convert and upgrade all the PCs in the department to the latest release of a specific desktop application. Prior to this conversion, all manner of desktop software existed on machines throughout the company and had caused increasing problems with sharing files and information across the company. A lot of unproductive hours were spent typing information into several formats. This project came about as a result of which of the following? A. Technological advance B. Business need C. Customer request D. Legal requirement

573


You are the project manager for the Late Night Smooth Jazz Club chain, with stores in 12 states. Smooth Jazz is considering opening a new club in Arizona or Nevada. You have derived the following information: Project Arizona: Payback period is 18 months, and the NPV is 250. Project Nevada: Payback period is 24 months, and the NPV is 300. Which project would you recommend to the selection committee? A. Project Arizona because the payback period is shorter than Project Nevada B. Project Nevada because the NPV is a positive number C. Project Arizona because the NPV is a negative number D. Project Nevada because the NPV is a higher number than Project Arizona's NPV

609


You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. The manager of the R&D department has agreed to release two resources to work on your project in order to meet the federal grant application date. This is an example of: A. Crashing B. Fast trucking C. Resource leveling D. Adjusting the resource calendar

660


You are the project manager for Heart of Texas casual clothing company. They're introducing a new line of clothing called Black Sheep Ranch Wear. You will outsource the production of this clothing line to a vendor. The vendor has requested a SOW. All of the following are true except: A. The SOW contains a description of the new clothing line. B. As the purchaser, you are required to write the SOW. C. The SOW contains the objectives of the project. D. The vendor requires a SOW to determine if they can produce the clothing line given the very detailed specifications of this project.

513


Which of the following is true regarding the project charter? A. The project charter should be published under the name of a manager external to the project. B. The project charter should be published under the project sponsor's name. C. The project charter should be published under the name of the project manager. D. The project charter should be published under the name of the project champion.

629


Change control system, configuration management, performance measurement, additional planning, and project management information system are tools and techniques of which process? A. Integrated Change Control B. Scope Change Control C. Schedule change control D. Cost change control

507


How do you ensure that your project is always on track?

501


Obtaining formal project plan approval and sign-off is important for all of the following reasons except: A. Stakeholders are able to recommend a project Planning methodology to follow throughout the remaining process groups. B. Stakeholders are aware of the project details, which make them more likely to participate in future project decisions. C. Stakeholders will be more likely to cooperate. D. Stakeholders are aware of the specific details regarding project schedules, budgets, and risks.

906


You are a project manager for Bluebird Technologies. Bluebird writes custom billing applications for several industries. One of your users verbally requests changes to one of the screen displays. You explain to her that the change needs to go through the change control system. You explain that a change control system does all of the following, except: A. Document procedures for change requests B. Track the status of change requests C. Describe the management impacts of change D. Determine if changes are approved or denied

573